CCS ON THE UP

Port Douglas & Mossman Gazette - - NEWS -

Moss­man Mill plant avail­abil­ity was above bud­get for Week 7 along with the bud­geted through­put. The fac­tory pro­cessed 48,559 tonnes of cane at an av­er­age crush­ing rate of 338 t/hr. The ma­jor down time dur­ing the week was due to a shred­der ham­mer tip in­spec­tion, No3 Mill feed chute fault and No3 Mill steam en­gine is­sue. No6 Mill has con­tin­ued to per­form this week and re­sulted in im­proved crush­ing rates. CCS for week was 12.39. The av­er­age CCS to date is 11.97. To­tal cane crushed to date: 259,447 tonnes.