MOSSMAN CRUSH WEEK 8

Port Douglas & Mossman Gazette - - NEWS -

Mossman Mill plant avail­abil­ity was be­low bud­get for Week 8 but weekly through­put was above tar­get. The fac­tory pro­cessed 37,482 tonnes of cane at an av­er­age crush­ing rate of 329 t/hr. Two ma­jor down time events oc­curred dur­ing the week. A pin­ion gear on the drive for the cane car­rier failed, and the bagasse re­claimer failed. Ad­van­tage was taken of this down­time in other parts of the fac­tory and no sched­uled main­te­nance day was re­quired this week. CCS for the week was 12.84. CCS av­er­age to date is 12.08. CCS last week was 12.39.