The Gold Coast Bulletin

BACK TO WORK GUYS

But some tradies say it’s not worth it

- RYAN KEEN AND SALLY COATES

HUNDREDS of workers abruptly laid off the Gold Coast’s biggest constructi­on site Jewel have been told to return from Monday – but some say it is not worth their while.

In the first breakthrou­gh since work halted on the $1.4 billion beach-edge triple towers two weeks ago, a union meeting on site yesterday endorsed a return to the job. However, some contractor­s said they “didn’t really care” about the restart as ”there is not much work to finish”.

Mayor Tom Tate blasted the decision to return to work as a “stunt”, saying it was up to the developer and “no one else”.

HUNDREDS of workers abruptly laid off the Gold Coast’s biggest constructi­on site Jewel have been told to return from Monday – but some say it is not worth their while.

In the first breakthrou­gh since work halted on the $1.4 billion beach-edge triple towers two weeks ago, a union meeting on site yesterday endorsed a return to the job.

Soon after, a source said Jewel’s major builder Multiplex had contacted contractor­s to say the site would restart from Monday.

Not everyone is celebratin­g. One contractor said they “don’t really care” about the restart as in some cases it amounted to a few weeks work to complete certain halffinish­ed jobs. “There is not much work to finish. I’m more concerned that they come through for the other stuff already purchased,” the contractor said, adding many were awaiting six-figure payments for materials.

Work won’t begin immediatel­y due to several hurdles, including several days worth of crane and hoist safety checks required plus regatherin­g the 900 workforce that was axed or quit the site.

Officially as of yesterday, the Constructi­on, Mining, Forestry and Engineerin­g Union (CFMEU) estimated about half – about 450 – had been let go.

Another contractor said: “I let go five people and there’s probably another five that will come once it settles.

“It’s the first time our company has had to do it. It’s probably the worst timing because we have two other buildings finishing this week.

“Everyone was meant to be moving to Jewel and now I can’t move them. If I’d known months ago I would have been readjustin­g staff levels so it’s really thrown the whole company off,” the contractor said.

Despite a green light to return, CFMEU assistant secretary constructi­on Jade Ingham said safety checks were required then an “orderly resumption of work will continue”.

Mr Ingham said workers had certainty now through to Christmas either with the work scheduled or payouts.

“It depends on each contract whether work will last until after Christmas or (if not) workers will have entitlemen­ts through to Christmas, a redundancy package.”

Developer Yuhu Group has said some work is awaiting finalisati­on of designs and will be retendered – it is also saying a hotel operator will be chosen within weeks. The Bulletin revealed yesterday it was “almost certainly” going to be Marriott Internatio­nal’s luxury St Regis brand.

In a statement yesterday about the work restart, Yuhu Group said: “It is a very encouragin­g developmen­t and we look forward to work recommenci­ng on what is a vitally important project both for our company and the Gold Coast.”

It is understood $300 million worth of work is still to be done to complete the Jewel.

 ??  ??
 ??  ??
 ?? Picture: GLENN HAMPSON ?? A number of contractor­s say it is hardly worth their while to return to the Jewel worksite when it reopens on Monday.
Picture: GLENN HAMPSON A number of contractor­s say it is hardly worth their while to return to the Jewel worksite when it reopens on Monday.

Newspapers in English

Newspapers from Australia