MMRDA to com­plete con­struc­tion of Kherwadi fly­over by April 2015

Accommodation Times - - News -

The con­struc­tion of the north­bound arm of the Kherwadi Junc­tion fly­over has be­gun and will be com­pleted by April 2015. The south­bound arm of the Kherwadi fly­over was opened for traf­fic in June this year. “The 580-me­ter North bound stretch will be com­pleted by April 2015. While the South­bound arm was com­pleted in 225 days, we aim to fin­ish the North bound lane as sched­uled,” said Mr. Dilip Kawathkar, Joint Project Di­rec­tor (PR), MMRDA.