Business Standard

Why arbitratio­n has not worked

- MEGHA MANCHANDA

It has been almost a year since the government moved a step closer to addressing the logjam in the road sector. As of March 31, 2015, the National Highways Authority of India (NHAI) had pending arbitratio­n awards worth ~2,20,000 crore with its concession­aires.

The government had approved various measures to revive the “stressed” constructi­on space, including a cabinetapp­roved proposal that allowed government agencies to deposit up to 75 per cent of an arbitral award amount in an escrow account against a margin-free bank guarantee in cases where the award is challenged. However, legal experts say the move is yet to deliver the desired results.

According to the NHAI, just 65 claims, worth ~26,300 crore, have been submitted by road developers in 19 cases. As of May 26, ~9,800 crore has been released or settled against the margin-free bank guarantees.

A recent report by India Ratings and Research (Ind-Ra) points out that the settlement of arbitratio­n claims has been slow because of the inability of road developers to provide bank guarantees and open escrow accounts. The government’s initiative to release 75 per cent of the locked amount in arbitratio­n awards has had a limited impact on the liquidity of developers as banks have been wary of taking exposure through bank guarantees without adequate margins or collateral, according to the report.

The scheme was approved by the Cabinet Committee on Economic Affairs in August last year and the NHAI started accepting claims from December last year.

According to legal experts, there are various reasons why it has not been easy for project developers to take the arbitratio­n route. “The big part of the problem is in the ambiguitie­s in the project definition at the time of bidding, misleading site status and preparedne­ss mentioned in the RFP (Request for Proposal), vagueness in the concession agreement and the illogical transfer of some risks to the developers/contractor­s when they are in no position to manage such risks,” says Ramesh Vaidyanath­an, managing partner, Advaya Legal.

The quality of arbitrator­s appointed was another reason, say some experts. There has been a tendency to appeal most of the awards, largely out of fear of investigat­ion by vigilance department­s. Until recently, there was no mechanism to identify the bona fides of claims and push for an amicable settlement. A conciliati­on structure has been put in place recently and its efficacy still needs to be tested, say experts.

Some critics are of the view that the NHAI should not have taken the arbitratio­n route at all. “Arbitratio­n to begin with was not needed. Why should a company be compensate­d if the project is delayed?” says another legal expert.

An NHAI official points out that since arbitratio­n disburseme­nt is subject to the submission of a bank guarantee (BG), some companies are giving BGs in a piecemeal manner, which is causing a delay in the process.

According to the plan, the escrow account could be used to repay bank loans or meet commitment­s in ongoing projects. This was seen as a major step that will allow recoveries of loans by banks while enabling constructi­on companies to speed up execution. This was also expected to increase the ability of constructi­on companies to bid for new contracts in a competitiv­e environmen­t, helping government to contain the cost of public works.

The plan also drew up a specific standard operating procedure (SOP) that the NHAI had to follow at the time of arbitratio­n. Arbitratio­n was applicable to all NHAI projects in which the concession­aire and the Authority entered into an agreement, and in which the Arbitral Tribunal has passed the arbitral award in favour of the concession­aire and the NHAI has challenged it.

In cases where the arbitratio­n proceeding­s are under process under the provisions of the pre-amended Arbitratio­n Act, the Authority would send a communicat­ion to the contractor to give their consent within the period specified to switch to the amended provisions of the Arbitratio­n Act. There is also a robust monitoring mechanism for all cases in which funds have been disbursed by the Authority against a bank guarantee.

Another government interventi­on — looking at why arbitratio­n has not worked for the stressed road projects — may be par for the course.

 ??  ??

Newspapers in English

Newspapers from India