Project Progress 10% Start 01 Jan­uary 2014 End 31 De­cem­ber 2014

Insurance - - CBP UPDATES -

Mile­stones Achieved:

• The RFI for eCon­tent de­vel­op­ment was com­pleted be­tween 8 Jan­uary and 17 Jan­uary 2014. Four­teen Ven­dors par­tic­i­pated in the RFI ses­sions • The OLC Ten­der Brief­ing was con­ducted on 24 Jan­uary 2014 • Eval­u­ated the first stage of the OLC Ten­der: Com­pli­ance Stage • The OLC Ten­der Com­mit­tee Brief­ing was con­ducted on 25 Fe­bru­ary 2014.

Next Mile­stones:

• To con­duct the Ten­der Tech­ni­cal Pre­sen­ta­tion in sec­ond week of March 2014

• To eval­u­ate the 2nd Stage of the OLC Ten­der: Tech­ni­cal Stage • To iden­tify and ap­point SME for the OLC project