Western Leader

Three options for plant

- SIMON SMITH

The water treatment plant in Titirangi was built in 1929 and now needs replacing, Watercare says.

The Auckland Council controlled organisati­on is now consulting on three options: replacing the current plant, building on adjacent land or building on a third site in Oratia.

Operations manager Priyan Perera said that not only is the current plant old, requiring repairs and maintenanc­e, but new filtration technology is needed as the dams contain increasing amounts of cyanobacte­ria and algae.

‘‘It’s an old plant and it wasn’t designed to deal with what’s coming at it now,’’ Perera said.

‘‘It’s about the future, because the water is going to change and we can see that it has changed already.’’

The cost of building a new plant and associated pipes was ’’in the $300 million to $400m range’’ depending on the site and the ‘‘complexity and challenges of constructi­on’’.

Perera said no decision has yet been made about where the new plant would be built. ‘‘We have not made a choice, because we understand that there will be community issues,’’ he said. ‘‘There’s a lot to talk about and we want to communicat­e with people.’’

Watercare spokeswoma­n Maxine Clayton said community focus groups were held in November

‘‘It's an old plant and it wasn't designed to deal with what's coming at it now’’

Priyan Perera

2015. Forty-four potential sites were initially considered, and a Tonkin and Taylor report in June 2016 narrowed eight possible locations down to three.

The report said building on the existing site would require the rest of the water supply network to pick up the plant’s capacity while it is rebuilt.

The top option was to build on Watercare’s land on 130 Parker Rd in Oratia and on surroundin­g properties. ‘‘The site is large, with two alternativ­e water treatment plant locations within the site, and it is located at a very good elevation,’’ it said.

‘‘The presence of a Significan­t Ecological Area across most of the water treatment plant and reservoir sites constitute­s a significan­t hurdle from a consenting perspectiv­e and also means the social impacts are potentiall­y high.’’

Perera said the Huia Water Treatment Plant in Titirangi was the fourth largest in the country and supplied 19 per cent of Auckland’s water.

Its replacemen­t will be one of the biggest water treatment infrastruc­ture projects in the country ‘‘for a while’’, he said.

Watercare is holding public informatio­n evenings in the area on February 21, 22 and March 1. Go to watercare.co.nz for details.

 ?? SUPPLIED ?? Watercare’s map showing three possible replacemen­t sites for the aging plant.
SUPPLIED Watercare’s map showing three possible replacemen­t sites for the aging plant.
 ?? SIMON SMITH/FAIRFAX NZ ?? Priyan Perera.
SIMON SMITH/FAIRFAX NZ Priyan Perera.

Newspapers in English

Newspapers from New Zealand