EL into Al­ter­na­tive En­ergy in Thatta

Enterprise - - NEWS -

The fi­nan­cial de­tails of the 49.5 MW wind power pro­ject at Jhim­pir, Thatta have en­tered fi­nal­iza­tion stages. The pro­ject is a de­vel­op­ment pur­suit of En­ergy Lim­ited (EL), an in­de­pen­dent power pro­ducer sub­sidiary of Fauji Fer­til­izer Com­pany.

The EL has re­ceived the letter of in­tent from Al­ter­na­tive En­ergy De­vel­op­ment Board, while ADEB has also pro­vided the land for this pro­ject.

Nordex is sup­ply­ing the wind tur­bines of 1.5 MW ca­pac­ity while the Na­tional Elec­tric Power Reg­u­la­tory Au­thor­ity is draw­ing up the tar­iff. The es­ti­mated com­ple­tion time is re­ported to be 16 months