Bridge link to Tsolo

- SIKHO NTSHOBANE MTHATHA BUREAU sikhon@dispatch.co.za

A state-of-the-art Mabey steel bridge built by Mhlontlo municipal bosses with materials bought from the UK cost a little over R1.9m.

The total cost of the project is around R18m.

The bulk of the infrastruc­ture project, R16.1m, was spent on building a 15km access road to the new facility.

The Daily Dispatch reported last week that a new bridge had been built connecting Ngqakaqhen­i residents and others from more than 20 other villages to the rest of Tsolo.

ECM Technologi­es’ sales engineer Martin Venter, whose company helped buy the steel from overseas for Mhlontlo municipali­ty, said the bridge was a smart and sustainabl­e infrastruc­ture solution.

He said they built Mabey bridges in Tsomo and in the Free State province in 2009 and 2010.

Mhlontlo municipal spokespers­on Sisa Mpehle said constructi­ng the access road included building up a road bed and wearing course, constructi­ng dish drains and putting up stormwater drainage systems.

There were also labour costs as well as sub-contractor­s and consultant­s’ fees.