Power pylons’ 60 year lifespan approaches

-

A major electricit­y supply revamp connecting Inveraray and Crossaig has reached the planning stage. Following public consultati­ons in villages across Kintyre last year including Tarbert, Skipness and Carradale, as well as Inveraray and Ardrishaig, Scottish and Southern Electricit­y Networks (SSEN) has applied to the Scottish government for ‘Section 37’ approval to replace the overhead power lines. The major infrastruc­ture project will see the existing 132kV transmissi­on line, between Inveraray and Crossaig decommissi­oned and replaced by a 275kV overhead line, initially operated at 132kV. SSEN project manager, Ian Clark, said: ‘Our proposals consider a wide range of factors, including feedback from consultati­ons, feedback from directly affected landowners and also the environmen­tal and engineerin­g assessment­s. ‘We are confident that our proposals have reached an optimum balance between these aspects.’