project notes

Homebuilding & Renovating - - PORTFOLIO -

sup­pli­ers

Ar­chi­tec­ture team Archer and Braun Ar­chi­tects: archerand­braun.com Main con­trac­tor TrendHomes Ltd: trendhomes.co.uk Brick fac­ings Ib­stock: ib­stock.com Win­dows

Velfac: velfac.co.uk; brid­erand­bull.com Oak floor­ing Russ­wood: russ­wood.co.uk San­i­tary­ware

CP Hart: cphart.co.uk Car­rara mar­ble shower wall, van­ity and work­tops Rossi Stone: rossi­s­toneworks.com Black taps Dorn­bracht: dorn­bracht.com/en-gb Tiles So­lus tiles: so­lusce­ram­ics.com Fur­ni­ture SCP: scp.co.uk Iron­mon­gery SDS London: sd­slon­don.co.uk Paint (Slate I, II, III, IV)

Paint and Pa­per library: paintand­pa­per­li­brary.com

Build time­line

Bought the house 2014 Work com­menced Nov 2016 Com­pleted Mar 2017

Build costs

Glaz­ing £4,000 Floor­ing (exc. bath­rooms

and kitchens) £3,500 Kitchen

(inc. floor­ing) £6,500 Bath­room

(inc. floor­ing) £8,500 Be­spoke joinery

(kitchen, bath­room, bed­room,

TV unit) £16,500

Dec­o­ra­tion £12,000 Fit-out (plas­ter­board, ceil­ings, walls, doors, fit­ting of san­i­tary­ware/

kitchen items) £12,000

Me­chan­i­cal £9,500

Elec­tri­cal £5,500 Build­ing shell

and struc­ture £37,000

TO­TAL £115,000

the floor­plan

The main liv­ing ar­eas were opened up to max­imise nat­u­ral light. A more ver­sa­tile kitchen re­placed the orig­i­nal gal­ley style but the en­trance hall­way was re­tained. A bed­room and some stor­age space on the first floor were sac­ri­ficed for a larger bath­room.