Time­line of how costs es­cA­lAted

The Peterborough Evening Telegraph - - Event -

Fe­bru­ary 2014 - The es­ti­mated cost for the pro­ject rises from £11 mil­lion to £12 mil­lion. The works then be­gin to widen the park­way from two to three lanes in each di­rec­tion be­tween junc­tion 1 and junc­tion 2 (Gold­hay Way/Mal­borne Way round­about). Jan­uary 2015 - Peter­bor­ough City Coun­cil ap­proves an ex­tra £4.5 mil­lion for the pro­ject af­ter prob­lems emerge in­clud­ing soil con­tam­i­na­tion. The coun­cil cab­i­net hits back at claims of mis­man­age­ment. Fe­bru­ary 2015 - The de­ci­sion to spend the ex­tra £4.5 mil­lion is calledin, but de­mands for an in­ves­ti­ga­tion are re­jected by coun­cil­lors. Septem­ber 2016 - Another £830,000 for the works is ap­proved.