Spring finish for flood relief work Speed read...

Borough: Second phase of works will finish next year

- By Adrian Williams adrianw@baylismedi­a.co.uk @AdrianW_BM

Works on the Jubilee River which were intended to finish in December will now continue into March. The relief channel protects 3,200 homes on the riverside and there are fears the delay will leave them at greater risk of flooding.

Works on the Jubilee River flood relief channel will not be complete before March 2021 – bringing fears of greater flood risk for houses on the riverside.

The Jubilee River diverts water from the Thames upstream of Maidenhead. It reduces flood risk to approximat­ely 3,200 homes in Cookham, Maidenhead, Windsor and Eton.

At the beginning of November, work was set to begin on the erosion of

Black Potts weir in Windsor. A routine dive found erosion to the downstream area of the weir.

The work was originally planned to continue throughout December but now will run until March.

Until the update is complete, the channel can only operate at ‘reduced capacity’, in the words of the Environmen­t Agency (EA).

In an update on the works, the EA wrote: “The River Thames needs long and continuous days of rain to flood, providing us with ample time to prepare for any flooding.

“We have implemente­d

temporary changes to how we operate the Thames upstream and downstream of the Jubilee River to ensure the Thames stays at a constant level.”

However, councillor Ewan Larcombe of the National Flood Prevention Party (Datchet, Horton and Wraysbury) is not convinced by this.

“I wonder about the competence of the EA,” he said. “This is yet another structural failure – the Jubilee River has been dogged by them.

“The erosion should never have happened, it’s substandar­d in design and constructi­on. It has never been able to carry its design capacity. It is unusable at the moment, and now Maidenhead is back to the place it was in 2002.”

An Environmen­t Agency spokespers­on said: “Since October we have carried out more on site surveys to

Black Potts weir and it has become clearer what we need to do to complete the permanent repairs. The second phase of the works, to be completed in the New Year, will allow us to safeguard repairs using heavy rock armour and ensure that the weir will continue to operate long into the future. We still intend to complete the first phase of the repairs, giving us operationa­l capability of the channel, by Christmas as initially intended.

“Decisions over how much flow we pass down the channel will take into account flood risk to people and property and also the safety of the weir and the railway viaduct. Our approach to managing this will be risk-based depending on weather and river conditions, so there is no definitive figure on the capacity of the channel before completion of the repairs.”

 ??  ?? Work at Black Potts weir on the Jubilee River is expected to run until March 2021. Ref:133103-7
Work at Black Potts weir on the Jubilee River is expected to run until March 2021. Ref:133103-7