The Denver Post

AUDITOR FINDS $2.9M FAILURE AT DIA

DIA’s runway review lapse cost the airport after extensive pavement cracking.

- By Jon Murray The Denver Post Jon Murray: 303-954-1405, jmurray@denverpost.com or @JonMurray

DIA’s failure to review technical standards for airfield projects contribute­d to extensive cracking of new pavement on a runway and cost DIA $2.9 million.

Denver Internatio­nal Airport’s failure to review technical standards for airfield projects contribute­d to extensive cracking of new pavement on a runway and cost DIA $2.9 million, city auditors reported Thursday.

DIA was on the hook for that amount on the major 2015 runway pavement replacemen­t project because the contractor had followed the airport’s technical specificat­ions for pavement mixing, the audit found. The airport accepted partial responsibi­lity and paid the settlement to Flatiron Constructo­rs for work to replace 49 of 150 damaged concrete panels on the runway, on top of its $35.4 million contract. The rest of the panels were sealed.

The extra payment was revealed by an audit that looked at two large airfield constructi­on projects managed by DIA’s Airport Infrastruc­ture Management Division, which oversees maintenanc­e of runways, apron pavement and taxiways.

“Specifical­ly, we found that the AIM Division lacks a sufficient process by which to ensure that the technical specificat­ions provided to the contractor have been reviewed and approved,” the audit says.

For the runway project, the audit says DIA relied on an old modificati­on to its pavement standards, which are based on Federal Aviation Administra­tion specificat­ions. But that modified standard for the concrete mix was unnecessar­y, the report says. The modificati­on resulted in the production of excessive heat as the pavement solidified, damaging 150 of 700 poured panels.

“After the panel cracking incident, (the airport) took measures to improve its controls surroundin­g its project technical specificat­ions,” the audit says, including an outside review of its standards by an engineerin­g consultant.

In his response to the audit, Mark A. Baker, DIA’s senior vice president of airport infrastruc­ture management, agreed to a recommenda­tion for another safeguard. The project office will create a process to review technical specs for each project for accuracy and completene­ss before soliciting bids.

DIA agreed to implement several other audit recommenda­tions by the end of September, including changes to ensure that bid documents are maintained properly and that bid advertisem­ents no longer include incorrect or conflictin­g informatio­n about submission deadlines and other aspects.

Auditors found those issues on at least one bid, suggesting they “could result in questions about the integrity of the bid process.”

Newspapers in English

Newspapers from United States