New Straits Times

PM: 6 months of rain caused Kelantan, Terengganu floods

Unpreceden­ted rainfall behind severe flooding in Terengganu and Kelantan, says PM

- HANA NAZ HARUN KUALA LUMPUR news@nst.com.my Natural Disasters · Disasters · Terengganu · Dewan Rakyat · East Coast · Kota Bharu · Kota · Pahang · Sabah · Sarawak · Beijing · United States of America · United States Armed Forces · Anwar Ibrahim · Tumpat · California State Route 1 · Pasir Mas · Rantau Panjang · Machang · Kuala Krai · Syed Saddiq Abdul Rahman

DATUK Seri Anwar Ibrahim tells Parliament the ‘extraordin­arily high rainfall’ was beyond expectatio­ns and the resulting deluge caused RM1 billion in damage. He says Phase 1 flood mitigation projects are on schedule and further work is being expedited.

THE unpreceden­ted deluge at the end of November dumped more than six months of rainfall in just five days, causing severe flooding across Kelantan and Terengganu.

Prime Minister Datuk Seri Anwar Ibrahim said between Nov 26 and 30, the rainfall recorded at the Drainage and Irrigation Department stations in Tanah Merah and Tumpat, for example, had exceeded 1,167mm of rain in just five days.

“According to the Meteorolog­ical Department, the reading (in Kelantan) was at 1,442mm, which is an extraordin­arily high level of rainfall.

“In Terengganu, the department’s Besut station recorded 1,761mm of rain during the same period. Overall, the rainfall was at 1,349mm, which is far beyond expectatio­ns.

“The five-day rainfall total was more than six months’ worth of average rainfall,” Anwar told the Dewan Rakyat during the Prime Minister’s Question Time.

He was responding to Datuk Mumtaz Md Nawi (PN-Tumpat), who asked if the Disaster Risk Reduction policy would be accelerate­d to allow all major flood mitigation facilities to be expedited, including the East Coast Highway 3 project.

Anwar said for flood mitigation projects, Phase 1 covering Tumpat and part of Pasir Mas was 70 per cent complete, and was expected to be fully complete by early 2026.

Phase 2, covering Rantau Panjang and part of Pasir Mas, was being expedited and Phase 3 covering Tumpat, Tanah Merah, Pasir Mas and Jeli was four per cent complete.

“However, the Sungai Kelantan flood mitigation and river management project is nearly complete, in which Phase 1 covering Kota Baru, Tumpat, Tanah Merah, Machang and Kuala Krai is 98 per cent complete, and Phase 2 covering Kota Baru has just started this year and is four per cent complete.”

In Terengganu, he said, the flood mitigation scheme in Kemasik was 91.8 per cent completed and was expected to be fully operationa­l by the end of January next year, whereas the Sungai Tepoh and Benggol Air Lilih schemes had just begun.

The three flood mitigation schemes in Terengganu include the Sungai Besut Phase 1, Gong Kiat and Guntung Luar schemes.

“The flood forecastin­g and warning programme is also quite advanced, and this flood prediction model system uses a hydrodynam­ic approach,” said Anwar.

“Flood simulation­s are generated by combining various inputs, including hydrologic­al data from the programme’s telemetry stations and rainfall forecasts from MetMalaysi­a, which uses a numerical weather prediction model that incorporat­es satellite and radar technology.”

Meanwhile, the cost of damage caused by floods had reached RM1 billion, with the repair of schools, hospitals and roads being the priority.

“We are waiting for detailed informatio­n on the overall situation. Right now, it seems to have eased slightly in Kelantan and Terengganu, but it has worsened in Pahang, and it is forecasted that Johor will also be affected.

“I assure you that immediate needs, such as food, water and basic facilities, including repairing damaged roads, will be prioritise­d,” Anwar added.

He also confirmed that ongoing flood mitigation projects, including those in the east coast, were on schedule, despite being initially cancelled in 2022 for re-tendering.

Anwar said the decision was made after the Madani government took over, rejecting direct negotiatio­ns which were deemed to be based on “weak foundation­s”.

“To date, the projects are still on schedule, except for one in Terengganu, if I’m not mistaken. It has not been disrupted.

“We have records that through the tender process, we saved a significan­t amount of funds compared with what was originally allocated.”

Torrential rain caused by the annual northeast monsoon has led to severe flooding in several states, including Kelantan, Terengganu, Kedah and Perlis.

Anwar said while technical and financial evaluation­s by the Finance Ministry must be adhered to, he assured that the process would not cause delays in the completion of the flood mitigation projects.

He said this in response to a supplement­ary question from Syed Saddiq Syed Abdul Rahman (Muda-Muar) regarding whether there was any evidence of misconduct in the tender process for the previously cancelled flood mitigation projects.

Anwar said the government had spent close to RM15 billion for flood mitigation projects throughout the country, including in Sabah and Sarawak.

“There is no country that can guarantee flooding won’t occur; even advanced nations like China, the United States and Europe can’t fully control it. But our efforts must remain strong.”

Additional measures, he said, included advanced monitoring systems for flood alerts and more effective mitigation projects.

Page 1 pic: Two women consoling each other in front of their homes destroyed by floods in Kampung Jubakar Pantai in Tumpat, Kelantan, yesterday.

 ?? ??
 ?? NSTP PIC BY NIK ABDULLAH NIK OMAR ?? Several houses that bore the brunt of floods in Kampung Jubakar Pantai in Tumpat yesterday.
NSTP PIC BY NIK ABDULLAH NIK OMAR Several houses that bore the brunt of floods in Kampung Jubakar Pantai in Tumpat yesterday.

Newspapers in English

Newspapers from Malaysia