Architecture Australia

Room for (in)novation: Responsibi­lities of and liabilitie­s for architects

- Words by Bronwyn Weir

In light of the Lacrosse decision, constructi­on lawyer Bronwyn Weir suggests ways in which architects can better protect themselves.

Many were surprised by Judge Ted Woodward’s decision in the Victorian Civil and Administra­tive Tribunal hearing regarding the fire at Melbourne’s Lacrosse Tower.1 The builder was not apportione­d a share of damages despite having undertaken to design and construct the building. Instead, the builder was able to deflect responsibi­lity for non-compliant work to its consultant­s, namely the building surveyor, architect and fire safety engineer.

The decision, now under appeal, has caused many architects to question the impact of novation on their ability to perform their work and how they can best manage liability.

What was the Lacrosse case about?

The Lacrosse building, a twenty-one-storey residentia­l and retail tower in Docklands, Melbourne, was constructe­d between

2010 and 2012. On 24 November 2014, a fire occurred as a result of an occupier leaving a cigarette in a plastic food container on a balcony table. The fire spread rapidly up the building via the highly combustibl­e aluminium composite panels on the facade, rising thirteen storeys in about twelve minutes. Approximat­ely four hundred people were evacuated but there were no serious injuries.

The focus of the tribunal was on the selection, approval and installati­on of the aluminium composite panels used as cladding. The owners sought damages from the builder, claiming it had breached statutory warranties by installing noncomplia­nt cladding. The builder joined various parties, including the building surveyor, fire safety engineer and architect, all of whom had been novated to the builder as consultant­s under a design and construct contract.

While the builder and its three consultant­s were all found to have breached their respective contracts, the builder was found to have reasonably relied on the other three consultant­s, to whom 97 percent of the damages payable by the builder were apportione­d.

The architect’s conduct

The architect specified that the aluminium composite panel (ACP) cladding for the balconies was to be “indicative to Alucobond.” During constructi­on, a substitute product – later found to be highly combustibl­e and therefore non-compliant – was used. In its defence, the architect argued that the novated contract passed all responsibi­lity for the design from the architect to the builder.

The tribunal disagreed, finding that the services the architect agreed to provide in its consultant agreement included the preparatio­n of contract material that would satisfy the legislativ­e requiremen­ts applicable to the design, including those of the Building Code of Australia (BCA). Having found that the ACP product used was not compliant with the BCA, it followed that the architect’s conduct in specifying “indicative to Alucobond” was in breach of the contract.2

This decision confirms that courts will expect architects to prepare documents that demonstrat­e BCA compliance. The involvemen­t of other specialist consultant­s does not relieve the architect from its obligation to understand and apply the

BCA to its design.

Novation and the role of the builder under a “design and construct” arrangemen­t

In April 2019, the Australian Institute of Architects conducted a national survey on the outcomes of procuremen­t methods that involve novation of the architect.3 Among Victorian respondent­s, the survey found that where a novated contract was in place: rates of product substituti­on were higher and more likely to have a negative impact on finish and durability; there was lower commitment to ecological­ly sustainabl­e design; architects were less likely to be included in project control meetings and they reported being denied site access; builders were more likely to take shortcuts in certificat­ion; architects had increasing responsibi­lities for all aspects of constructi­on yet diminishin­g power and influence over design and constructa­bility outcomes; the contractua­l terms required by the builder impacted negatively on the architect’s ability to deliver quality outcomes; the architect was less likely to be able to protect the interests of the developer; and architects were often unable to increase their fees to suit increased workloads, leading to an inability to provide adequate resources and to adverse health and wellbeing outcomes for staff.

Some of the findings of the Institute’s survey are consistent with the evidence given by the architect in the Lacrosse matter. In the hearing, the architect reported a lack of consultati­on and a failure by the builder to ask for or take the architect’s advice.4 The architect argued that its role was diminished, that it was not treated as the “head design consultant” and that it therefore should not be attributed responsibi­lity for that role. In the tribunal’s opinion, however, the actual relationsh­ip did not override the contractua­l obligation­s.

In light of the Lacrosse case and the results of the Institute’s novation survey, there are ways that architects can better protect themselves. They must understand clearly what obligation­s they are agreeing to under any contract and price their services accordingl­y.

Where they are unable to obtain enough informatio­n to do that, their price should be appropriat­ely qualified.

During the project, where the architect is being prevented from performing its services – such as being denied access to the site or not being included in essential meetings – it needs to raise these matters with the builder in writing, referring to its rights and any remedies it may have under the contract. The ability to seek additional fees will depend on the terms of the contract. Unless an architect has negotiated the ability to increase fees based on clearly defined events, the only way to mitigate against increases in scope will be via contingenc­ies that are priced into the original fees.

Put simply, the contract you sign can only protect you if it has been negotiated fairly and if you enforce your contractua­l rights when you are being prevented from performing your role.

It is vital for those in the profession to support each other in order to reach a common position on what is acceptable and to lift the benchmark for fair contractin­g. — Bronwyn Weir is the co-author of the Building

Confidence Report. She has more than twenty years’ experience advising government­s on regulatory issues.

Footnotes 1. Owners Corporatio­n No. 1 of PS613436T v L. U. Simon Builders Pty Ltd (Building and Property) [2019] VCAT 286, 28 February 2019, vcat.vic.gov.au/resources /ownerscorp­oration-no1-of-ps613436t-owners-corporatio­n-no-2of-ps613436t-owners (accessed 17 September 2019). 2. Owners Corporatio­n No. 1 of PS613436T v L. U. Simon Builders Pty Ltd (Building and Property), 159–160. 3. Australian Institute of Architects, “The benefits and challenges of novation for architects – Victoria,” August 2019, architectu­re.com.au /wp-content/uploads/ Australian-Institute-of-Architects_Novation-Survey_ Victoria-2019.pdf (accessed 17 September 2019). 4. Owners Corporatio­n No. 1 of PS613436T v L. U. Simon Builders Pty Ltd (Building and Property), 149.

Newspapers in English

Newspapers from Australia