The Australian Mining Review

OZ Minerals

On the back of a productive year, OZ Minerals remains focussed on developing one of Australia’s largest copper gold resources, Carrapatee­na, with first concentrat­e scheduled in 2019.

- JESSICA CUMMINS

AS the Adelaide- based miner moves its Carrapatee­na project towards production, a number of key activities remain on the table.

After injecting $ 85 million into the project during the September quarter, the miner saw the completion of its first ventilatio­n raisebore and commenced developmen­t on the crusher level.

OZ Minerals chief executive Andrew Cole said flights to the site had begun and constructi­on of all 556 rooms at the Tjungu accommodat­ion village were also completed.

“The mineral processing plant and non- processing infrastruc­ture constructi­on is continuing as per schedule, with first concrete poured in late August,” Mr Cole said.

“Bulk earthworks and concrete works in the processing area are nearing completion and engineerin­g is largely complete with major equipment deliveries set to ramp up during Q4.”

For the remainder of the calendar year, works at the site would be focussed on ongoing decline developmen­t, additional ventilatio­n raisebores from surface, process plant constructi­on and borrow pit works.

Mr Cole said constructi­on would commence at the tailings storage facility, northern wellfield bore fit out, as well as improvemen­ts to the Southern Access road.

Mr Cole said Carrapatee­na expansion studies were also continuing with an expected maiden resource estimate for the Fremantle Doctor prospect due in Q4 of calendar year.

“Diamond drilling has also commenced on the Punt Hill project, approximat­ely 50km south of Carrapatee­na and an update on the expansion desktop studies will be provided in Q1 2019,” he said.

The installati­on of its main communicat­ions network and high voltage powerline began during the second quarter of 2018, with completion scheduled for Q4 of calendar year

“Installati­on of the main communicat­ions fibre optic cable network and high voltage powerline is progressin­g well, with over 100 kilometres of cable installed from the Woomera Telstra Exchange to site,” Mr Cole said.

“The associated Mount Gunston ElectraNet Sub Station is nearing completion while earthworks and concrete infrastruc­ture for the ElectraNet Pernatty South substation is well- advanced.”

Exploratio­n

In October OZ Minerals met its $ 22 million spending commitment to acquire a 51 per cent stake in Cassini Resources’ West Musgrave project in WA.

A Pre Feasibilit­y Study was currently underway for the project, which was scheduled to be complete in the second quarter of 2019.

OZ Minerals still has the option to increase its stake further and earn up to 70 per cent by investing an additional $ 14 million towards Nebo- Babel studies and regional exploratio­n.

“The pace with which OZ Minerals have met the earn- in hurdle is significan­t as it shows the partners desire to progress rapidly through the study stage and the potential of the project,” Cassini Resources managing director Richard Bevan said at the time.

Mr Cole said the company’s confidence in the West Musgrave project continued to grow.

“Positive progress has been made across resource geology and recent metallurgi­cal test work has produced encouragin­g early results with improved recoveries for both copper and nickel,” Mr Cole said.

“Early metallurgi­cal test work on master composites, which represent different time periods of the current mine plan, has shown a material improvemen­t in copper and nickel recoveries and an increase in copper concentrat­e grade, while nickel recovery remains in line with the further scoping study.

“We will know more once results from the test work are provided following the completion of metallurgi­cal test work on variabilit­y samples from different geological domains in Q1 2019.”

Mr Cole said the 2018 resource drill program for West Musgrave was nearing completion, and because the company had been encouraged by the results decided to push the 2019 drill work forward.

Mr Cole said the company took a “province approach” to its operating mines, constructi­on sites, and exploratio­n projects.

“What this means is, rather than simply seeking to develop a single new mine, or single new opportunit­y, we look for copper rich provinces where initial or existing investment­s can serve as a launching platform or hub for other opportunit­ies,” he said.

“In the Musgrave province, we have the West Musgrave and East Musgrave projects.”

The East Musgrave prospect is about 500km east of the West Musgrave project.

“In addition to the work in West Musgrave, we also have an earn- in agreement with Woomera Exploratio­n Limited to explore for magmatic nickel and copper sulphides in the Eastern Musgrave province,” he said.

“We are currently looking at innovative applicatio­n of the Vector Residual Magnetic Intensity ( VRMI) technique, traditiona­lly used in iron ore and gold exploratio­n, to resolve prospectiv­e anomalies at East Musgrave.

“This exploratio­n joint venture targets magmatic nickel- copper sulphide systems like those of the Nebo Babel deposits in West Musgrave.”

Acquisitio­n

OZ Minerals has also been active in the M& A space gaining 100 per cent of Avanco Resources in a $ 418 million acquisitio­n in August.

Mr Cole said the acquisitio­n was consistent with the company’s strategy to become a multi- asset, copper core modern mining company.

“It also gave us the second largest land position in the highly prospectiv­e, world- class Carajas copper province – and the largest land position in the Gurupi greenstone gold belt in Brazil,” he said.

The package included one operating asset, two well progressed developmen­t projects and numerous high priority brownfield and regional exploratio­n targets.

“The acquisitio­n allowed us to immediatel­y contribute copper tonnes to our production profile and offered significan­t additional new growth options as well as a meaningful footprint in the highly prospectiv­e Carajás province,” he said.

“The acquisitio­n provides us with the potential of seeing seven mines up and operating within the next six years.”

Outlook

Mr Cole said the company had made significan­t progress on its growth strategy in 2018, and 2019 would follow in the same path.

With multiple projects fast tracking through the build and study phases, Mr Cole said OZ Minerals’ portfolio was what a healthy mining company should look like.

“We have put a few enablers in place to allow us to work towards our vision of becoming a global copper- core modern mining company by 2023,” he said.

“One of these enablers is our devolved model - which is more important than ever now that we have operations in Brazil, as it will empower our business to make decisions to achieve outcomes that they are accountabl­e for delivering.”

 ?? Allimages:OZMinerals. ?? Carrapatee­na airstrip.
Allimages:OZMinerals. Carrapatee­na airstrip.
 ??  ?? “We have put a few enablers in place to allow us to work towards our vision of becoming a global copper-core modern mining company by 2023.”
“We have put a few enablers in place to allow us to work towards our vision of becoming a global copper-core modern mining company by 2023.”
 ??  ?? “Opportunit­ies that attract us are ones that are aligned to our strategy, meet internal requiremen­t and are value accretive. Our targeting criteria is based on resource quality – quality of resource and bottom of cost curve.”
“Opportunit­ies that attract us are ones that are aligned to our strategy, meet internal requiremen­t and are value accretive. Our targeting criteria is based on resource quality – quality of resource and bottom of cost curve.”

Newspapers in English

Newspapers from Australia