The Australian Mining Review

Gruyere Gold Mine

The joint venture between Gold Road and Gold Fields looks set to deliver another tier one gold mine to WA.

- GERARD MCARTNEY

THE Gruyere joint venture is aiming to pour first gold during the June quarter, and anticipate­d full production by the end of 2019.

After a re-evaluation in 2018, the final forecast capital cost for constructi­on was estimated at $621 million, up from the initial capex of $507 million.

The project was expected to produce an annual average of 300,000 ounces over its 12-year mine life; about 30,000oz more than the 270,000ozpa originally flagged, making the project an emerging tier 1 gold producer.

In a statement, the company said that the increase was driven by the “opportunis­tic purchase of larger SAG and ball mills to lift throughput to 8.2million tonnes per annum (mtpa) in fresh rock from 2021.”

At 14 February, the JV partners had mined 185,000 tonnes of ore, which created a substantia­l stockpile in preparatio­n for initial production.

In mid-February, the JV announced its annual guidance for 2019 would sit between 100,000 and 120,000oz, with an all-in sustaining cost of between $1050 and $1150 per ounce.

Downer, which was awarded a five-year $400 million mining services contract in December 2017, started double shift operations in January 2019 as a part of the production ramp up.

“It is good to see the Gruyere project develop from conceptual plans through feasibilit­y study to a well-designed large scale, long-life, low-cost operation that is on the threshold of delivering substantia­l value for our shareholde­rs,” Gold Road chairman Tim Netscher said.

The project would also see two additional ore sources added to the Gruyere pit that would increase its milling capacity from 7.5 million to 8.2 million tonnes.

The Mine

The Gruyere gold project was situated on the mining lease M38/1267, about 200km east of Laverton.

Pre-feasibilit­y was completed in February 2016, followed by a feasibilit­y study in October 2016.

The project was wholly owned by Gold Road until November 2016, when the company entered into the 50/50 joint venture agreement with South African giant Gold Fields, which paid $350 million and took on the developmen­t and operation of the project.

The sale provided 50 per cent of the required capital that, according to Gold Road, “de-risks the project to a significan­t degree through the introducti­on of a partner highly experience­d in the developmen­t and operation of open-pit gold mines that has agreed to cover any cost overrun up to 10 per cent of the total developmen­t budget.”

Constructi­on began in the second half of 2017, and will be completed by mid-2019.

Before production could begin, the JV partners contracted APA Group which would build, own and operate the site’s 45-megawatt gas-fired power station, and the 198km of new pipeline to connect the site to APA’s existing pipeline network.

To secure water for the Gruyere Village, GR Engineerin­g Services completed the constructi­on and commission­ing of six out of eight bores at the Anne Beadell borefield.

The Yeo borefield, which was to be used as the main source of water for the process plant, was developed jointly by MACA and the ACJV.

The total investment in constructi­on was more than $1 billion.

Heavy rain in the 2018 March quarter delayed the first gold pour as localised flooding led to access constraint­s at certain parts of the project, pushing the first pour back to the second quarter of 2019.

In June 2018, the company announced that as the project entered its critical phase of constructi­on and developmen­t, an independen­t review of the project determined an 8 per cent increase was necessary “after scope changes and force majeure,” saw production cost rise from $507 million to $621 million.

The project had begun recruiting and would require up to 350 staff, with the Gruyere JV requiring 90 new permanent staff, and Downer needing 154.

The company had offered an eight-days-on, six-days-off roster in order to attract workers.

Exploratio­n

The JV partners also continued to explore through the Gruyere JV tenements, with emphasis on the discovery of high-margin ore reserves that could supplement the Gruyere life-of-mine schedule.

The 14km Golden Highway had already defined 600,000 ounces, and infill drilling was completed at Montagne and Argos deposits.

These deposits were within economic haulage distance to Gruyere and could potentiall­y be exploited as satellite open pit mines that could increase the mine life of Gruyere.

In Gold Road’s 100 per cent owned northern and southern tenements, staged exploratio­n of the high-priority targets had considerab­le success.

The company’s past and planned expenditur­e would amount to about $70 million, and was moving toward resource definition at Gilmour, Smokebush and Corkwood, while continuing to make high grade bedrock intersecti­ons in early stage prospects and in new shallow gold anomalies.

Gold Road would focus its exploratio­n and evaluation efforts on defining deposits that could support the next significan­t standalone operations.

 ??  ??
 ??  ?? The mine purchased larger SAG and ball mills to increase throughput.
The mine purchased larger SAG and ball mills to increase throughput.
 ??  ?? There were 648 rooms installed at the Gruyere Village.
There were 648 rooms installed at the Gruyere Village.
 ??  ?? The Gruyere airstrip.
The Gruyere airstrip.

Newspapers in English

Newspapers from Australia