Newell night works

-

THE Department of Transport and Main Roads will undertake night works at the Newell Beach Boat Ramp until April. The following works schedule has been designed around tides: Jan 29 to Feb 4 – dredging and preparatio­n of the ramp; Feb 11-20 – precast footings installati­on for fixed walkway; Feb 27 to Mar 5 – planks installati­on for boat ramp; Mar 14 to Mar 20 – rock armour and shoulders installs; Mar 29 to April 2 – dates if required.