Newell night works
THE Department of Transport and Main Roads will undertake night works at the Newell Beach Boat Ramp until April. The following works schedule has been designed around tides: Jan 29 to Feb 4 – dredging and preparation of the ramp; Feb 11-20 – precast footings installation for fixed walkway; Feb 27 to Mar 5 – planks installation for boat ramp; Mar 14 to Mar 20 – rock armour and shoulders installs; Mar 29 to April 2 – dates if required.