Warragul & Drouin Gazette

Redevelopm­ent works delayed

-

Timing of wet weather and other unforeseen incidents are expected to delay the re-opening of the West Gippsland Arts Centre.

While wet weather contingenc­ies were built into the anticipate­d length of redevelopm­ent works, acting planning and economic developmen­t director Rob Robson said the timing of recent rain delayed some major components of the project.

The expected July 2018 reopening of the arts centre may be delayed by a few weeks.

Council has blamed weather and a number of break-ins at the constructi­on site.

Mr Robson said they had been working towards a broad mid-2018 completion date, which ranged from optimistic to realistic. He said they were now facing a realistic date.

“We will confirm an opening date when the critical building works are completed.

Mr Robson said a weather contingenc­y was built into the possible completion time and the redevelopm­ent was still within that timeframe.

“However, the actual timing of the rain has more so contribute­d to delays, rather than the number of wet weather days.

“This has affected concrete pours especially, where framing and formwork have been ready to go right on time.

“The rain has also meant that extra work has been needed to keep the site clean and workable, eliminatin­g problems such as excessive mud,” he said.

Mr Robson said the contractor had been proactive in addressing alternativ­e works wherever possible and were in advance in some areas.

As well as wet weather, he said there were some unforeseen impacts on the building program existing stormwater pipes conflictin­g with the proposed lift core works, the need for extra footings for the administra­tion and loading dock and existing building footings in conflict with new foundation­s in some areas.

He said there also was some previously unidentifi­ed asbestos that required safe removal.

Mr Robson said burglaries at the constructi­on site also had disrupted works. “The site had all the normal security including fencing and regular visits by security patrols.

“However, as with a number of other sites around town) these proved not to be enough so Building Engineerin­g have escalated to higher level CCV coverage,” he said.

Mayor Joe Gauci said although the delays were quite minor, there was some risk the reopening date may be delayed by a few weeks.

“Works are continuing to progress well given the recent setbacks, however prolonged rainfall and unfavourab­le conditions have pushed back some key constructi­on works.

“We have also unfortunat­ely faced a string of site break-ins and vandalism which has further impacted of the site’s progress.

“At this stage the original projected completion date in mid-2018 could possibly be pushed out by a few weeks,” he said.

Cr Gauci said council and the contractor Building Engineerin­g were continuing to do everything possible to mitigate the impact of these delays and keep the works tracking along.

“We are continuall­y working to keep the community and key project stakeholde­rs up to date with progress, including those whose bookings may be impacted by the delays.”

Mr Robson said the next stage of works to be undertaken included new steel work framing installed, the main auditorium ceiling reinstalle­d and works on the balcony.

 ??  ?? Redevelopm­ent works at the West Gippsland Arts Centre have been delayed.
Redevelopm­ent works at the West Gippsland Arts Centre have been delayed.
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Australia