Gulf Today

Kannur airport a story of engineerin­g marvel

- BY ASHRAF PADANNA

TRIVANDRUM: Kerala’s brand new Rs 18.92 billion Kannur airport on Wednesday released aerial photograph­s of the picturesqu­e terrain transforme­d into an engineerin­g marvel.

The airport company lattened around 700 acres of land for the operationa­l area on a terrain spread in seven valleys of different depths, varying from 36 meters to 86 metres.

Moorkkanpa­rampu, the place where the airport is located, was a rough terrain with several valleys where the land level was of a zigzag shape.

The authoritie­s say earthwork for levelling the area, especially the land required for the operationa­l area, was the biggest challenge before the team comprising engineers.

Constructi­on major Larson & Toubro received the contract in November 2013 and inished the 3050-mere runway and 84 per cent of the airside work by May 2016.

It took more than two years to inish the rest and almost all facilities, including six aerobridge­s, will be ready when it opens on Sunday.

The company had to spend around 48 per cent of the total cost of the operationa­l area for earthwork alone.

At some places, blasting was required to break the laterite, an excellent resource for constructi­on, mainly the compound wall, and soil used for illing the valleys.

“Before the terminal and runway were built, no constructi­on existed at the site. Weather and controllin­g the natural course of water were also a challenge,” said KP Jose, the executive director of Kannur Internatio­nal Airport Limited (KIAL).

“The engineerin­g team had to ensure that water low from the site mixed in mud lowing to the premises of the houses downhill was minimal. So we constructe­d outlets through which water lowed to two natural streams nearby.”

The highlight was the constructi­on of runway end safety area (Resa) on the western end limiting the consequenc­es when lights overrun during the landing or a rejected takeoff.

The 240 metre-resa mandatory as per internatio­nal standards is ixed on a 90 metre- high surface developed with 6.4 million cubic metres or around 710,000 truckloads of soil.

“It’s a tough engineerin­g task. With limited land available, the engineerin­g team had no option but to develop the surface to meet the internatio­nal standards of the runway,” a company release quoted him as saying.

Newspapers in English

Newspapers from Bahrain