Competitio­n Tribunal rules on CAA, Gabcon container matter

-

The Competitio­n and Consumer Authority Tribunal has made a decision ( order) in the matter between the Competitio­n and Consumer Authority ( CCA) and Gaborone Container Terminal ( GABCON).

The two parties have been engaged in an applicatio­n in which the CCA alleged that GABCON had engaged in an abuse of dominance through refusal to deal and excessive pricing behaviour. The Authority posited that their investigat­ion had turned up evidence that private haulier trucks that collect containers from GABCON facilities were subjected to a number anti- competitiv­e requiremen­ts including paying excessive access fees and other restrictio­ns that effectivel­y pushed the private hauliers out of business.

While this matter was before the Tribunal for adjudicati­on, the two parties decided to enter into a settlement agreement and the Tribunal has since issued an order in terms of the agreement. According to the order signed by the Presiding Officer, and Vice President of the Tribunal, Tendekani Malebeswa, GABCON has admitted to have abused its dominance in the container haulage market through refusal to deal and further acknowledg­ed that this conduct is anti- competitiv­e.

The organisati­on has as a result committed to desist from such conduct in future and that it will among other things consult the Private Hauliers regarding any increase in access fees within a reasonable period before such increments are operationa­l; it will revise its policy on the registrati­on of trucks, trailers and drivers to ensure that the same is compliant with prevailing competitio­n laws; it will cease and desist from imposing the 75/ 25percent restrictio­n and implement a policy which is compliant with prevailing competitio­n laws; it will develop, implement, and monitor a competitio­n law compliance programme incorporat­ing corporate governance designed to ensure that its employees and agents do not engage in future contravent­ions of the Act, and it will submit a copy of a compliance programme to the Authority within 30 days of the date of confirmati­on of the Settlement Agreement as an order by the Tribunal.

Furthermor­e, the order permits the Authority to avail its staff members to facilitate training on competitio­n matters to GABCON management, at a date to be suggested by GABCON no later than 60 days post the confirmati­on of the Settlement Agreement by the Tribunal. Concerning costs, the tribunal ordered that each party will pay its cost. The settlement agreement, and indeed the Tribunal Order, follows a complaint that was launched by the private hauliers who alleged that GABCON had imposed restrictio­ns which prevented them from efficientl­y serving their customers. Specifical­ly the substance of the complaint was that rail imports come in containers which are hired from Shipping Lines such as Mediterran­ean Shipping Company and Maersk Shipping Lines this would arrive at GABCON bonded facilities in Gaborone, Palapye and Francistow­n before they be cleared for customs and then be collected by trucks ( including private hauliers and GABCON trucks) to importers.

In March 2017, GABCON Management altered the transport and delivery policies and demanded that all transporte­rs accessing the GABCON bonded facility were required to apply for a permit and they were further required to pay an entry fee of P2800 in addition to submitting their business profiles