Botswana Guardian

P1.9 billion for 27km road

DIS halted tender award to launch investigat­ions Tender at evaluation stage - PPADB, MTC Transport Ministry looking for additional funds as project funding increases from P1.4 billion to P1.7 billion

- Nicholas Mokwena BG reporter

Controvers­y continues to shadow the constructi­on of the 27KM Mogoditsha­ne- Gabane- Mankgodi Junction Road since 2019 when the Directorat­e of Intelligen­ce and Security ( DIS) halted the award of a tender under the pretext of investigat­ing possible corruption.

The CONSTRUCTI­ON OF PULA SPAR MOGODITSHA­NE- GABANE - MMANKGODI TENDER NUMBER WORK 7/ 17/ 9( 1) was initially budgeted for P1.4 billion as per the Project Engineer’s estimates at the time of Tender Closing on April 24th of 2019.

However, investigat­ions have revealed that the budget for the Dual Lining Road ( dual carriage) has now been increased to P1.7 billion with a likelihood of reaching P1.9 billion.

Sources have revealed to this publicatio­n that while the DIS has completed its investigat­ions and found no flaws, the Directorat­e is plotting to have the tender awarded to its preferred Chinese Contractor with close ties within the government enclave.

According to informatio­n passed to this publicatio­n, Pula Consulting, which was appointed as lead Consultant­s, did the evaluation and recommende­d as follows: CC/ SS JV 96.5 percent; MGM JV TIEC/ CRIG 83.5 percent; CRSG- RAUBEX JV 82.6 percent; CCECC- LM- ZT JV 81.7 percent; and CFHEC & COLIC JV 79.8 percent.

The PPADB approved this recommenda­tion on the 17th of February 2021. DIS allegedly intervened and instructed the Ministry of Transport and Communicat­ions to suspend the award saying they are investigat­ing the tender. A two- man team of the DIS was assigned to investigat­e the matter. It is alleged that the DIS told the Ministry that OP has instructed them to investigat­e the tender, an instructio­n they refused to put in writing.

“The DIS officials took the tender document from the Ministry. After some time, they came back and gave the Ministry and consultant their recommenda­tions that were different from that of the Consultant.

“The ministry has been at pains to explain to stakeholde­rs why the tender was suspended. They wanted the DIS to explain to the stakeholde­rs but the DIS said the Ministry must do it. This cancellati­on of the award is going to attract price escalation,” a source revealed.

Sources in the constructi­on industry say that the DIS wants this tender to be awarded to a Chinese company. “Although they said there is corruption at the award of this tender, DCEC is not aware of these investigat­ions by the DIS,” added another source.

In an excuse for the delay of the award of the tender, the ministry is said to have indicated that since the budget has gone up to P1.7 billion, it is still sourcing funds to cover the P300 million excess of the initial budget.

The consultant and his evaluation team were allegedly summoned by the DIS a fortnight ago, trying to justify the delay of the award as approved by PPADB. While there are claims from the PPADB and the parent ministry to the effect that the tender is at the evaluation stage, records from both Kweneng District Council and Mogoditsha­ne/ Thamaga Sub Council show that the tender has since been awarded although the name of the contractor has not been disclosed. According to records seen by this publicatio­n, PPADB is still waiting for the ministry to avail Form 3 which speaks to the sourcing of additional funds. Botswana Guardian has also establishe­d that the road is expected to be done in two Phases due to the unavailabi­lity of funds. According to the Mogoditsha­ne/ Thamaga Sub District Developmen­t Committee Report, dated 9th - 13th August 2021, the planned date for the start of the constructi­on was July 2019.

The Report indicates that the status is that the PPADB on 29th April 2021 stood down the award of the tender pending the Ministry ( MTC) to submit PPADB Form 3 which is a tool confirming the availabili­ty of funds. The ministry, according to the Report is still addressing the matter.

PPADB could not be drawn into responding to the questions regarding the tender. “We are not in a position to answer the questions raised as the tender is still under adjudicati­on and therefore remains confidenti­al in terms of Section 91 of the Procuremen­t and Asset Disposal Act,” Public Relations and Education Manager Charles Keikotlhae said. Ministry of Transport and Communicat­ions through its Public Relations Office said it is not aware of the suspension of this tender. And on that basis, the ministry said it would not comment on whether the DIS declined to put their instructio­n in writing and if the suspension of the award of the tender was communicat­ed with stakeholde­rs. It further stated that the tender is at the adjudicati­on stage with PPADB. Pula Consulting declined to comment on the issues referring this publicatio­n to the Director of Roads Department. Both DIS and the DCEC had not responded to questionna­ires sent through their public relations offices and the follow- ups made at press time.

Newspapers in English

Newspapers from Botswana