Botswana Guardian

Defects stalk Morupule B Power Plant

Power plant continues producing less than capacity Remedial work for all 4 units to be completed in 2024

-

Ten years later, the 600 MW Morupule B Power Station in Palapye continues to generate less power than its design capacity due to a perpetuati­on of defects.

This was revealed this week by Minister of Mineral Resources, Green Technology and Energy Security, Lefoko Moagi during his ministry’s committee of supply presentati­on for the 2022/ 23 budget.

The 600 megawatt coal fired Morupule B plant, which was commission­ed in 2012 and built by China National Electric Equipment Corporatio­n ( CNEEC) at a cost of P11.5 billion, has often broken down, leading to a reliance on diesel generators and imports from South Africa. The first Morupule B units were commission­ed in 2012 but unit one was taken off- stream on January 15th 2013 after developing cracks in its primary and secondary air ducts. At some point, government was said to be planning to sell the plant.

Minister Moagi told Parliament this week that remedial works on the plant are on- going and currently, this power plant is generating 380MW from three of its four units, being unit 1 ( 150MW), units 2 ( 80MW) and 3 ( 150MW). He stated that Boiler heat exchangers are the major components that require replacemen­t on all the four units with a new design as these pieces of equipment have exhibited perennial failures since the first commission­ing of the plant. Moagi revealed that the remedial works on Unit 4 which commenced in June 2019 were delayed due to the Covid- 19 Global Pandemic which prevented service providers based in China from mobilizing and providing the required services at site.

“However, the Unit is now undergoing recommissi­oning of the boiler and turbine where major remedial works were undertaken. Remedial works on all the four units are expected to be completed by end of 2024 after which the plant will be generating at its design capacity of 600MW on firm basis. In the meantime, the diesel based power generators at Matshelaga­bedi and Orapa power peaking plants continue to be deployed in cases of power supply shortfalls experience­d intermitte­ntly,” said Moagi.

According to the Minister in 2020, Government approved the Integrated Energy Resource Plan ( IRP) to guide Botswana’s power generation build programme over the next 20 years.

As part of the implementa­tion of the IRP Road Map for the programme, Moagi indicated that Government has already embarked on developmen­t of a 300MW Coal Fired Power Station ( greenfield), 200MW Concentrat­ed Solar Thermal Power Station ( CSP), 100MW solar photovolta­ic ( PV) together with 12 solar PV grid- tied power plants with a total net generation capacity of 35MW around the country.

He pointed out that most of the projects are renewable and green technologi­es and the objective of the programme is to increase contributi­on of renewable energy technologi­es to local power generation capacity for the country.

“This will help reduce the internatio­nal pressure arising from the need for addressing climate change matters such as reducing and mitigating the country’s carbon foot print. This follows the commitment made at the Conference of Parties ( COP26) on Climate Change. Notable progress on the implementa­tion of Green Energy Technology initiative­s is being attained,” he said.

The Minister told Parliament that under developmen­t Budget for the Ministry, the Rural Electrific­ation and Network extension programme has been allocated the third largest share of the Developmen­t Budget at P44 100 000 or five per cent. He said the proposal is for works earmarked for 79 villages under this programme being connection of 29 new villages and 50 network extensions.

The Power Generation and Distributi­on programme takes the fourth largest share of P36 060 000 or about four percent, adding that the provision is towards continuati­on of the Backbone Power Transmissi­on projects of Mochudi, Tlokweng and Ramotswa, as well as the Provision of Services for Power Supply Build Programme, said the minister.

 ?? ??

Newspapers in English

Newspapers from Botswana