The Voice (Botswana)

LIGHTS OUT

• BPC disconnect over 1,600 defaulters • Raise P109 million from the exercise

- BY BAITSHEPI SEKGWENG

Early this year, local power utility Botswana Power Corporatio­n (BPC) embarked on an exercise to disconnect all commercial businesses which defaulted in payments.

As a result 1,612 commercial customers were disconnect­ed while P109 million was collected in arrears.

Speaking to Voice Money, BPC Communicat­ions and Marketing Manager, Dineo Seleke, warned this was just the beginning.

“The Corporatio­n will continue the debt collection exercise on accounts under arrears as part of the usual business mode. The collection campaign really assisted because the debtor days, which were as high as 55 days, reduced to 33 as of the end of May. That means on average the corporatio­n is owed just above a month’s possible collection­s,” she explained.

Seleke said various economical factors, compounded by the Covid-19 pandemic, have affected small and medium businesses, making it tougher for them to meet their obligation with BPC.

“Almost all households are on prepaid, save for those using maximum demand capacity. The bulk of arrears relate to accumulate­d balances prior to conversion to prepaid. Government debtors average two months and they revolve while the mines have been paying very well within a month of invoicing,” she continued.

Meanwhile, remedial works continue at Morupule B Power Station to address equipment and constructi­on defects from the original project completed in 2014.

The project scope includes replacemen­t of unreliable and defective major boiler components. Remedial works for unit 1 began in June 2019 and were successful­ly commission­ed and tested this June.

The unit is currently undergoing a 90day trial run and is expected to be handed back to BPC in October.

DISCONNECT­ED: BPC have disconnect­ed 1,612

Unit 2 will then undergo a year’s worth of repairs and are forecast to be finished next October. Repairs will begin on the third and fourth units in November 2023 and February 2024, with the work expected to be complete by October 2024 and January 2025 respective­ly.

 ?? ??
 ?? ?? TOUGH TALK: Dineo Seleke
TOUGH TALK: Dineo Seleke

Newspapers in English

Newspapers from Botswana