Calgary Herald

Landowners suing to derail power lines

Claim argues Alta link line wrongly OK’d

- SHEILA PRATT

The seven-year battle over two new north-south transmissi­on lines could heat up again with a pending court challenge designed to derail both lines.

A new lawsuit will argue the province had no jurisdicti­on to designate as necessary Altalink’s $1.5-billion western transmissi­on line because it will be used to export electricit­y and, as such, falls under federal jurisdicti­on.

Two Calgary area landowners hope their lawsuit will force the National Energy Board to review both the western and eastern transmissi­on lines.

The lawsuit will also argue the Alberta Utilities Commission did not have jurisdicti­on to require ratepayers to pay for the new lines or to approve the routes because the lines are under federal jurisdicti­on, said lawyer Donald Bur.

Both those decisions were taken by the AUC in December after hearings this summer into Alta link’s $1.5-billion western line from Genesse west of Edmonton to Langdon south of Calgary and ATCO’s $1.4-billion eastern Alberta line ending in Brooks.

Amy and Neil Cunningham, who own land near Calgary, filed papers Friday requesting leave to appeal to the Alberta Court of Appeal.

If leave is granted, the lawsuit could derail both projects, which are already under constructi­on.

Altalink’s 350-kilometre western line would be built to handle 1,000 megawatts of power, but could be increased to handle 4,000 megawatts and would be complete in two years.

In an interview from Toronto, Bur noted that originally the Alberta government set conditions so ratepayers would not pay for the portion of any new power lines devoted to export. Companies were required to designate what share of a new line would be used for exports.

Since then, the province has maintained the new transmissi­on lines are not for export but are needed to meet growing demand for power in Alberta.

The AUC has said the line is not an export line because lies entirely inside Alberta.

“They keep saying these lines are needed. But southern Alberta, where the lines end, does not need additional power,” Bur said.

This fall, in granting approval to Altalink’s western line, the AUC said the line is also intended “to restore capacity” to the existing tie line between Alberta and B.C.

That’s a clear signal the goal is to enhance exports to B.C, he said.

Alberta already imports B.C. power and exports power west when demand here is low.

An enhanced interprovi­ncial electricit­y line would have to be approved by the NEB, just as the Northern Gateway pipeline to ship Alberta bitumen to B.C is the subject of an NEB hearing, said Bur.

The government has also argued it needs to reduce congestion on the grid, that there is too much power in the north and not enough capacity in the power lines to move the power to other areas where it is needed.

That may be the case, said Bur. But Alberta wants to reduce congestion by exporting electricit­y to B.C. or the U.S., and that puts the new lines in federal jurisdicti­on.

“If these are interprovi­ncial lines, the utilities commission has no right to sayratepay­ers have to foot the bill,” he said.

The proposed northsouth grid expansion was derailed in 2007 after a scandal erupted when private investigat­ors were hired to spy on landowners opposed to the western line. The province aborted the public hearing process and in 2009 declared both north-south lines were critical infrastruc­ture under the Electric Statutes Amendment Act or Bill 50.

That power to declare the lines necessary without a hearing was repealed last fall.

ATCO’s eastern line will end in Brooks. That raises the question of whether an export line would be built later to tie the ATCO southern power station into the U.S.

They keep saying these lines are needed. But southern Alberta, where the lines end, does not need additional power DONALD BUR

Newspapers in English

Newspapers from Canada