First Nation, Focus plan power project

- DAN BARNES

EDMONTON — Paul First Nation leaders say they are committed to providing an alternativ­e to the coal-fired power plants that have for decades cast a shadow over the 1,900-member reserve, located 70 kilometres­westofEdmo­nton.The First Nation announced recently it has formed a partnershi­p with developmen­t company Focus Equities on a proposed 1,000-megawatt, gas-fired power plant that would cost about $1 billion to build and would be connected to the provincial grid.

Plans are to build the Great Spirit Power Project in one phase — four gas-fired turbines in combinatio­n with two steam turbines — and have the 30-month constructi­on on Paul First Nation industrial park land completed in 2017.

It would be the largest single-phase power project in the province.

“As a nation that lives in the shadow of large, aging coal plants, we are proud to be a part of such an environmen­tally friendly project that will provide social, health-re- lated and economic benefits for our people and other Treaty 6 Nations,” said Chief Casey Bird.

There is an opportunit­y for five to seven other First Nations to join the Ironhead First Nations Partnershi­p, founded by Paul First Nation for the purposes of this power project. Focus Equities will be the project lead, while First Nations participan­ts will earn an equity stake.

Terence de Pentheny O’Kelly, Focus Equities vice-president of energy, said his firm’s executives have decades of experience working on power plants in Virginia, Huntington Beach, Calif., Fort Lupton, Colo., and elsewhere in the world, but none in Canada.

The Alberta Electric System Operator received formal notificati­on of the proposal on Jan. 20, said spokeswoma­n Dawn Delaney.

“From the AESO’s perspectiv­e, we’re pleased to receive their formal notificati­on that they plan to move forward. We’re adding that project to our project list and we’re co-ordinating a meeting with the project team. That would include the AESO, the market participan­t, in this case the Great Spirit Power Project, and the TFO, the transmissi­on facility owner, which will be ATCO.”

Once added to the AESO project list, it would bring proposed future output to about 10,000 megawatts of gas-fired, solar and windpowere­d generation.

“We’re looking at 6,000 megawatts of generation that will be required by 2022,” said Delaney.

“It’s to respond to growing demand as well as a replacemen­t for those retiring coal units. The coal retirement­s account for about 720 megawatts of the 6,000 megawatts.”

While it is the province’s most ambitious project, de Pentheny O’Kelly said he doesn’t see this as an overbuild.

“From a macro-economic perspectiv­e, there is a huge need for power in the province in the decade ahead. The power demand will double and coal plants are coming offline. There is an enormous supply gap that needs to be filled. We’re confident the demand will be there.”

Focus Equities and Paul First Nation first worked together on an unsuccessf­ul bid to build the Fort McMurray West Transmissi­on line.

“We developed a great relationsh­ip with them,” said de Pentheny O’Kelly.

“Chief Casey Bird approached us, saying, ‘The coal plants are going to be coming offline. Would you guys be interested in working with us to develop replacemen­t capacity?’”

He said the next steps include securing equipment suppliers for the turbines — likely to originate in Germany, Japan or the United States — as well as lining up contractor­s and submitting an applicatio­n to the Alberta Utilities Commission.

 ?? Postmedia News/Files ?? Paul First Nation is proposing a gas-fuelled power plant to replace coal power such as that provided by TransAlta’s Sundance power plant.
Postmedia News/Files Paul First Nation is proposing a gas-fuelled power plant to replace coal power such as that provided by TransAlta’s Sundance power plant.

Newspapers in English