Calgary Herald

Burnaby battles pipeline

Kinder Morgan expansion at survey stage

- DENE MOORE THE CANADIAN PRESS

VANCOUVER — Kinder Morgan took its fight with the City of Burnaby, B.C., directly to residents on Friday, the latest salvo in an ongoing feud over the proposed expansion of its Trans Mountain pipeline.

A letter distribute­d to residents near the company’s Westridge marine terminal in Burnaby blamed city council for blocking its survey crews from Burnaby Mountain, home to Simon Fraser University and a expansive conservati­on area.

Kinder Morgan’s preferred route through the mountain would avoid residentia­l neighbourh­oods, the company told residents.

“The ability to route through Burnaby Mountain would avoid several private homeowners and minimize community disruption­s,” the letter said.

If the company is unable to com- plete those studies soon, “we may have to pursue our alternate route through city streets.”

Crews will conduct survey work in the residentia­l neighbourh­ood over the next week, it said.

“As we have not yet been able to fully explore the Burnaby Mountain route, we need to continue our planning and work for the neighbourh­ood route as well,” the letter said.

“I cannot emphasize strongly enough this is not our preferred option, and we would much prefer to work together with residents in order to minimize impacts.”

Kinder Morgan and the city have been in an escalating battle over the $5.4-billion Trans Mountain expansion between the Alberta oilsands and a tanker terminal in Metro Vancouver.

The expansion would almost triple the pipeline’s capacity, from 300,000 barrels a day to about 900,000 barrels.

Vancouver city council is also opposed to the project but it is particular­ly controvers­ial in Burnaby, where Kinder Morgan was fined for a 2007 constructi­on accident along the pipeline that rained 230,000 litres of oil down on a neighbourh­ood.

For its part, Burnaby council tried and failed this week to win the support of convention delegates at the Union of B.C. Municipali­ties annual meeting on a motion to oppose the pipeline.

It was a narrow loss. The resolution was defeated by a margin of 50.7 per cent against and 49.3 per cent in favour, following a debate that touched on issues including the likelihood of an oil tanker spill to the increase in oil-by-rail through the province’s Interior region.

Municipal leaders did vote in favour of a Burnaby resolution calling for change to the regulatory hearing process.

Under new rules, the National Energy Board has opted against allowing intervener­s to directly question the company. All comment must be submitted in writing.

The dispute has already set the regulatory review for the pipeline back seven months. A final report from the energy board panel to cabinet is now due Jan. 25, 2016.

The report could be further delayed, after the NEB dismissed a Kinder Morgan request for the federal regulator to bar the City of Burnaby from blocking survey work on the mountain.

Earlier this month, Burnaby halted survey crews on the mountain, saying they were cutting down trees and boring large holes in the ground in violation of city bylaws.

The city unsuccessf­ully sought a court injunction, but Trans Mountain said it would not resume work until the issue was resolved. It then filed the motion with the regulator.

In a decision released Thursday, a board panel found Kinder Morgan was essentiall­y asking them to override the city bylaws.

“In the board’s view, this clearly raises a constituti­onal question,” the panel wrote.

The company will have to inform the federal and provincial attorneys general and raise specifical­ly that constituti­onal question about the regulator’s legal authority, the board said.

Trans Mountain spokeswoma­n Lizette Parsons Bell said the company is reviewing the decision and considerin­g the next steps.

“We have no intention of resuming invasive work in Burnaby Mountain Conversati­on Area,” she said.

 ?? Arlen Redekop/postmedia News ?? A crew conducts geotechnic­al work in Burnaby, B.C. for Kinder Morgan’s Trans Mountain expansion.
Arlen Redekop/postmedia News A crew conducts geotechnic­al work in Burnaby, B.C. for Kinder Morgan’s Trans Mountain expansion.