Calgary Herald

North Dakota pipeline going ahead despite protests

- TIM LOH Bloomberg

Energy Transfer Partners said Thursday that its Dakota Access crude pipeline, plagued by protests for months, is still set to be in service by spring. Donald Trump’s election, meanwhile, means business is “only going to get better,” the company’s leader said.

Constructi­on on the $3.8-billion line is nearly complete in North Dakota, where the pipeline giant is waiting for an easement from the U.S. Army Corps of Engineers to drill a final segment beneath Lake Oahe, company officials said on a call with analysts.

Once it receives the easement, Energy Transfer can begin a threeto-four month drilling program and draw the remaining $1.4 billion from a $2.5-billion credit facility that’s financing the project.

Energy Transfer Partners is at the centre of a battle over new pipelines proposed across the U.S. Its 1,900-kilometre Dakota Access line has become a rallying point for the anti-fossil fuel movement and is facing opposition from Native Americans who say it’ll damage culturally significan­t sites.

Trump has voiced support for energy infrastruc­ture and has stressed the need to speed up regulatory reviews for projects.

Energy Transfer CEO Kelcy Warren said he was “stunned” by Trump’s victory and that the pipeline operator now finds itself in a good position.

“I’m very, very enthusiast­ic about what’s going to happen with our country,” he said.

Energy Transfer’s under no legal obligation to stop constructi­on on the Dakota Access project and hasn’t voluntaril­y agreed to do so, despite requests from the U.S. Army Corps, company officials said. It has finished 84 per cent of the project and is pushing ahead with constructi­on wherever it’s permitted, including in Iowa.