Bitumen is still seeping, years after drilling halted

Primrose site north of Cold Lake a concern for area First Nation

- BOB WEBER

Environmen­talists and First Nations are raising concerns about a heavy oilfield in northeaste­rn Alberta that may still be seeping water and bitumen years after the flow was first discovered.

The field, owned by Canadian Natural Resources Ltd., was the subject of a major investigat­ion by the province’s energy regulator after a major “flow-to-surface event” in 2013.

Surface water collected near four fissures in the ground continues to show an oily sheen. The Alberta Energy Regulator says a fifth, which first leaked in 2009, stills oozes small amounts of fresh bitumen.

The regulator says the situation is well-managed and CNRL considers the leak over and cleanup complete.

Fraser Thompson of the environmen­tal law firm Ecojustice said it’s disturbing the leakage may be ongoing.

“There’s reason to be concerned that after what’s been about 3 1/2 years, the bitumen is still coming to the surface and the AER hasn’t been able to tell us when it’s going to stop.”

In June 2013, the Alberta Energy Regulator reported a leak in CNRL’s Primrose field near Cold Lake, Alta. Eventually, it emerged that nearly a million litres of bitumen mixed with water had seeped from fissures in the ground.

In a report released in the spring, the regulator blamed CNRL’s extraction method, which depended on injecting waves of high-pressure steam undergroun­d to soften the bitumen and force it toward collection wells from where it was pumped. The company was using too much pressure, the report concluded.

The regulator required CNRL to use a different approach, with lower steam pressures, and granted permission for the company to resume production from the field.

Surface water from the four sites involved in the 2013 leak continues to show effects, confirmed Julie Woo of CNRL.

“Bitumen seepage is not present in the surface run-off water currently being collected at the sites. That said, the water may contain a residual sheen.”

Bitumen continues to seep from the 2009 site, said AER spokeswoma­n Carrie Rosa.

“That first flow-to-surface still experience­s occasional seepages,” she said.

“When it’s cold and frozen, the flow will stop. It is very, very slow and very, very minimal.”

The regulator, which has its own field inspectors, doesn’t have informatio­n on how much has leaked. The water and the bitumen are collected and kept out of the ecosystem, Rosa said.

Crystal Lameman, treaty co-ordinator for the Beaver Lake Cree First Nation, said her band has had concerns about the site since 2008 and is in court trying to get access to it. The site is within the band’s traditiona­l territory.

The band is worried about the cumulative effects of heavy industry impact on its land.

 ?? ED KAISER/FILES ?? Oil glistens off the water as booms line a marsh near Canadian Natural Resources Ltd.’s Primrose oilsands project in an attempt to contain bitumen seeping to the surface in 2013.
ED KAISER/FILES Oil glistens off the water as booms line a marsh near Canadian Natural Resources Ltd.’s Primrose oilsands project in an attempt to contain bitumen seeping to the surface in 2013.

Newspapers in English

Newspapers from Canada