Two steps forward in Canada’s pipeline dance

- CHRIS VARCOE

Take two steps forward, a halfstep back.

The Canadian pipeline dance marathon never seems to end and the music is always playing.

But the country is inching closer to building new oil pipelines as current ones run full and domestic prices suffer.

Ever so slowly, progress is being made.

“We are getting positive momentum,” said Chris Bloomer, CEO of the Canadian Energy Pipeline Associatio­n.

“It is painful at times, but there is optimism that at some point they’re going to go.”

On Thursday, two key developmen­ts unfolded in Canada’s long-running pipeline logjam, coming after a half-step back on Wednesday.

TransCanad­a Corp. said it has commercial support for its US$8-billion Keystone XL pipeline, which would run from the Hardisty area south to Steele City, Neb.

Later in the day, Kinder Morgan won a pivotal ruling from the National Energy Board to streamline the dispute-resolution process to obtain municipal and provincial permits needed to build its Trans Mountain expansion. Both are hopeful signs for a Canadian industry that has been missing out on the recent oil price rally due to deepening discounts for domestic heavy crude.

For TransCanad­a, it would have been more of a surprise if the Calgary-based company said it didn’t have enough producers lined up to move oil on the 830,000-barrel-aday Keystone XL line.

There should be ample demand for the project as oilsands production continues to grow, and more crude is shipped by rail.

TransCanad­a announced it has secured firm 20-year contracts to transport about 500,000 barrels per day on KXL, “positionin­g the proposed project to proceed.”

Thursday’s news is not a fullfledge­d final investment decision to start building, although the company is one step closer to making that call.

“I would expect them to have an affirmativ­e decision, if not by end of January, then by the end of next month,” said retired TransCanad­a executive Dennis McConaghy. “You’ve got both Donald Trump and Rachel Notley aligned with this project. That’s an extraordin­ary accomplish­ment and it speaks to the inherent economic viability of the project.”

Companies such as Canadian Natural Resources and Suncor Energy have signalled their commitment to ship barrels on the cross-border pipeline. The Alberta government has agreed to transport 50,000 barrels a day of oil that the province collects from producers in place of royalties.

Alberta said it made the decision because the project will help shrink the differenti­al affecting Canadian heavy oil that’s costing companies and the province billions of dollars in lost revenue.

Some will argue the government’s commitment is a subsidy, but that won’t get much political traction. The government has a duty to maximize the value it can get from these barrels, and for all oilsands resources.

If the provincial agreement helps build a pipeline and shrinks the light-heavy oil differenti­al, the decision is “a sensible thing to do,” said economist Trevor Tombe at the University of Calgary.

A number of factors are now lining up in favour of Keystone XL being built, although nothing should be taken for granted, given the project was seemingly DOA a couple of years ago.

While TransCanad­a edged forward Thursday, the Trans Mountain expansion project also made some headway.

The National Energy Board ruled in favour of Kinder Morgan’s request to set up a generic process to quickly handle future disputes over constructi­on permits needed from municipal and provincial government­s.

The decision won’t win many friends in the B.C. government, which opposes the project, but it will be welcomed in Alberta.

Trans Mountain is favoured by the Notley government because it would triple the amount of oil moving on an existing line to the west coast. The project would give Canada more access to growing export markets, particular­ly in Asia.

The ruling comes after Kinder Morgan warned Wednesday the project is now a full year behind schedule, with an expected startup in December 2020.

More concerning is the fact the company hasn’t fully opened the project’s spending spigot yet, even with regulatory and federal approvals in hand.

Kinder Morgan CEO Steve Kean told a conference call that, until the U.S. firm receives greater clarity on permitting, it wouldn’t fully open the taps on the $7.4-billion developmen­t.

“We do need to see that there’s a process in place ... so that once we start, we can be confident that we are going to finish,” he said.

From a risk management point of view, it makes perfect sense. Who wants to invest billions of dollars in a project that might not cross the finish line?

For Canadian producers who watched the light-heavy oil price differenti­al widen to more than $29.64 a barrel on Wednesday, new pipeline capacity can’t come fast enough.

Nick Schultz with the Canadian Associatio­n of Petroleum Producers pointed out current pipelines in Western Canada — with a capacity of about four million barrels a day — are already full.

“We needed those pipelines now,” he said of the proposed developmen­ts. “That’s a negative for everyone in Alberta and, frankly, negative for Canada as a whole.”

 ??  ??
 ?? THE CANADIAN PRESS ?? TransCanad­a Corp. says it has commercial support for its US$8-billion Keystone XL pipeline, which would run from the Hardisty area south to Steele City, Neb. The company announced it has secured firm 20-year contracts to transport about 500,000 barrels...
THE CANADIAN PRESS TransCanad­a Corp. says it has commercial support for its US$8-billion Keystone XL pipeline, which would run from the Hardisty area south to Steele City, Neb. The company announced it has secured firm 20-year contracts to transport about 500,000 barrels...