Calgary Herald

TRANS MOUNTAIN CEO STILL HAS GOAL-LINE IN SIGHT

Anderson’s pipeline might not be on ‘one-yard line,’ but he is eyeing 2019 score

- CHRIS VARCOE Chris Varcoe is a Calgary Herald columnist.

Speaking before the Grey Cup last November, Premier Rachel Notley told a Calgary business audience that the Trans Mountain pipeline expansion was “on the one-yard line.”

To date, no touchdown has been scored. In fact, the ball has been moving in the wrong direction recently.

Today, the federally owned oil pipeline is stuck in limbo with no firm date for constructi­on to resume after a recent court ruling quashed its approval.

But the chief executive of Trans Mountain Corp., the federal Crown corporatio­n in charge of the oil pipeline, believes the project is still firmly within scoring range. Constructi­on could restart sometime in 2019, if problems identified by the judges are properly addressed.

“I think the quarterbac­k got sacked a couple of times and we may be back on the 25 (yard line) — you’re still in field goal range,” Ian Anderson told reporters Wednesday, before addressing the Internatio­nal Pipeline Conference in Calgary.

“I remain confident . . . I am just hopeful we can get through this next chapter and get back to work next year.”

Last month, the Federal Court of Appeal nullified the project’s approval, citing inadequate consultati­on with First Nations communitie­s by the government, and improper considerat­ion by the National Energy Board of the effect of tanker traffic tied to almost tripling the existing pipeline’s capacity.

The ruling put an immediate halt to constructi­on on the pipeline, which extends from the Edmonton area to Burnaby, B.C., and it put hundreds of contractor­s out of work. (About 2,000 people were working on the project at the time, a number that was expected to expand to 5,000 by January.)

Anderson, president of Kinder Morgan Canada since 2005 — until Ottawa bought the project this year — acknowledg­ed the recent court decision was a “shock that rippled through the company ... industry and government­s.

“Nobody had anticipate­d it,” he said. “In our view and the government’s view, the boxes were all ticked.”

But three federal judges didn’t agree.

New public hearings are expected to examine the effect of the project on marine-related traffic off the Pacific Coast, while meaningful consultati­ons with Indigenous communitie­s must also take place.

The project’s $7.4-billion price tag has been under pressure and will likely climb higher because of the delay.

While he doesn’t have an updated figure, Anderson said the latest setback will affect the planned December 2020 startup date — constructi­on will take about 30 months to complete — and that will have financial consequenc­es.

“There is no doubt that that (schedule) has slipped. How much it has slipped, I won’t know for some months,” he added.

“Time is money ... even if it’s just the carrying costs of what we’ve already spent, that’s money and that’s cost to the project.”

Constructi­on has been halted since last month’s ruling, although the Crown corporatio­n is trying to do all the preparatio­n work it can to be ready when the remaining hurdles are cleared.

Asked if it’s possible constructi­on could restart sometime next year, the 60-year-old executive said that could happen if the new NEB timelines on examining the effect of increased tanker traffic go smoothly, a recommenda­tion comes out in the middle of February and the federal government takes a few more months for additional consultati­on.

The problems that have plagued the Trans Mountain expansion have been painful, public and, it seems, neverendin­g, with more starts and stops than seen on Deerfoot Trail during rush hour.

Project proponent Kinder Morgan first submitted its applicatio­n for the project to the NEB back in 2013 and, after public hearings, it was approved by cabinet in 2016.

But the election of John Horgan’s government changed the dynamic, installing a fierce opponent to the pipeline in the British Columbia legislatur­e.

On the other side, the energy industry and Notley government see the project as an imperative for Alberta and Canada.

The price discount affecting Western Canadian Select heavy crude has hovered near all-time highs recently — it will cost the industry and government an estimated $15 billion this year — and petroleum producers are moving record amounts of oil by rail.

(Cenovus Energy announced three-year deals on Wednesday to ship about 100,000 barrels of heavy oil per day from northern Alberta to the U.S. Gulf Coast via railways.)

In the face of B.C.’s attempt to block the venture and more uncertaint­y ahead, Texas-based Kinder Morgan agreed to sell the pipeline this spring to the federal government for $4.5 billion.

Then the court ruling changed the game.

Last week, the Trudeau government gave the energy regulator 22 weeks to adequately reconsider the project’s effect on marine traffic.

The NEB announced Wednesday it will hold public hearings and report back no later than Feb. 22.

“There is no question we’ve had more barriers put in front of us than we had expected,” Notley told reporters Tuesday at the Internatio­nal Pipeline Conference.

“We are not people who see barriers and then turn around and walk away. We see barriers and we just climb over them.”

I don’t know how easy it will be to just “climb over” such formidable and important barriers, such as Indigenous consultati­on and marine safety. But it’s also not time to give up.

For Alberta and an oilpatch desperate to get its product to market, only a touchdown will do.

 ?? LEAH HENNEL ?? Trans Mountain CEO Ian Anderson, centre, says constructi­on could restart next year if problems identified by judges are addressed.
LEAH HENNEL Trans Mountain CEO Ian Anderson, centre, says constructi­on could restart next year if problems identified by judges are addressed.
 ??  ??

Newspapers in English

Newspapers from Canada