Calgary Herald

VEIL LIFTING ON OLD CITY HALL

Multi-year renovation concluding

- MADELINE SMITH masmith@postmedia.com Twitter.com/@meksmith

For three years, Calgary’s historic city hall has been just an image printed on a boxy enclosure at the corner of Macleod Trail and 7th Avenue S.E.

But the city says the real thing is finally ready to be unveiled after a restoratio­n job budgeted at $34 million.

The iconic downtown piece of Calgary’s history will be fully unwrapped by the end of June after nearly all of its 15,522 sandstone blocks were individual­ly rehabilita­ted. In some cases, pieces that deteriorat­ed too much have been replaced, and the city says the new blocks were “carefully selected” to make sure they match the original material.

About 2,400 new blocks of sandstone were used, according to the city. Replacemen­ts came from Ohio, Poland and Spain, but the Spanish stone is the closest to the sandstone taken from quarries that were open around Calgary when city hall was built at the turn of the 20th century.

The city also worked to stabilize the clock tower after discoverin­g it was leaning away from the building. Protective scaffoldin­g first went up around historic city hall in 2014 after chunks of sandstone fell off the exterior, which is more than a century old. A pre-design report later found that in addition to the crumbling sandstone facade, the building was also suffering from leaky windows and poor drainage — some of the exterior masonry was described as being in “critical” condition.

City council later approved a $35-million City- Owned Heritage Building Preservati­on Fund, virtually all of which was allocated to the Old City Hall project.

In 2017, a full enclosure was erected around the building as repair work began in earnest. The barrier allowed crews to work on the building no matter the season, which the city said helped make sure they finished the project on time.

The mayor, councillor­s and dozens of staff moved their offices into the city’s adjacent administra­tion building in 2016, and council voted in 2018 to move back into historic city hall once the work is done.

That decision came with an additional $400,000 price tag for renovation­s to accommodat­e additional staff. The city said at the time that plan would involve less renovation compared to letting the councillor­s stay in their temporary offices.

Council members and staff won’t relocate until at least September.

 ??  ??
 ?? GAVIN YOUNG ?? The constructi­on wrapping on the city’s historic city hall is scheduled to be removed in June after a three-year-restoratio­n. Work that cost $34 million involved extensive work on the sandstone facade, including replacing about 2,400 of the original blocks.
GAVIN YOUNG The constructi­on wrapping on the city’s historic city hall is scheduled to be removed in June after a three-year-restoratio­n. Work that cost $34 million involved extensive work on the sandstone facade, including replacing about 2,400 of the original blocks.

Newspapers in English

Newspapers from Canada