Calgary Herald

Green Line costs could go up amid `tough' market, councillor­s told

Project's price status shifts to `red' as board urged to address pressures

- SCOTT STRASSER

Costs for the Green Line LRT project are expected to escalate, but exactly how much won't be known until a revised business case is made public in June, according to officials.

Green Line board chair Don Fairborn and project CEO Darshpreet Bhatti presented the multibilli­on-dollar LRT project's first quarterly update of 2024 to the city's executive committee on Tuesday, highlighti­ng that constructi­on of the south leg of the future Ctrain line is expected to begin in the fall.

But due to higher-than-anticipate­d estimates from some of the project's subcontrac­tors, Bhatti warned the Green Line board may have to consider options to address cost pressures in the lead-up to constructi­on.

Those could include re-evaluating the procuremen­t strategy, amending risk-sharing allocation­s between the project team and contractor­s, or possibly revising the scope of the project.

“We constantly look at all these options while keeping one thing in mind — that the benefits cannot be compromise­d by what we're doing,” Bhatti said when presenting to the committee.

“There has to be a nice balance between benefits and risks.”

The current budget is $5.5 billion to construct the first phase, which will include 18 kilometres of lightrail track extending from Shepard in the southeast to Eau Claire in the downtown. The funding is being split between the city, provincial and federal government­s.

Bhatti's presentati­on Tuesday showed the Green Line's cost status has shifted from “amber” to “red.” He said this occurred after the project team received its developmen­t partners' most recent cost estimates in January, based on 30 per cent of the project's design.

“We always anticipate­d the market is tough,” he told the committee. “We're not the only project experienci­ng it, so we were always cautious about where this may go.”

After the meeting, Bhatti told reporters it's too soon to report an updated cost, as estimates from contractor­s only relate to a portion of the project's design.

But he acknowledg­ed the Green Line's budget was determined before the COVID-19 pandemic, and that inflationa­ry pressures have affected the market for infrastruc­ture projects since then.

“We're not the only project facing these challenges,” he said. “They are on every megaprojec­t, and even small projects are facing it.”

About $400 million has already been spent on the new Ctrain line that city council approved a revised version of in 2020.

Bhatti said the work delivered thus far has been on schedule and the team has been able to find hundreds of millions of dollars in engineerin­g efficienci­es.

He cited a decision to use a less expensive material for bridge decking on underpasse­s and overpasses than was originally planned — which he said trimmed $70 million from the budget.

“It meets all the standards and specs at the provincial level and the city level,” he said. “It's just a different way of doing it.”

Summarizin­g the work completed in 2024, Bhatti said a diversion track was laid in January on a temporary embankment at 78th Avenue S.E., and Canadian Pacific Kansas City rail traffic has been diverted to allow for constructi­on to begin on a vehicle and pedestrian tunnel.

Demolition of the former Lilydale chicken processing plant in Ramsay, which began in November, is complete, and Bhatti noted crews will start demolishin­g the Eau Claire Market this summer.

Other work underway this year includes relocating utilities in the Beltline and downtown, including transmissi­on line cable pulling and a major relocation of infrastruc­ture along Fifth Avenue, Sixth Avenue and Third Street S.W.

All land acquisitio­ns required before starting constructi­on are expected to be completed by the end of this month.

Public support for the project remains high, according to Bhatti. He noted that almost 90 per cent of 2,245 Calgarians surveyed last fall said they agree the Green Line is a necessary project.

Ward 1 Coun. Sonya Sharp said she supports the Green Line, as it will improve Calgary's public transporta­tion network, but that it's important for the project to have transparen­cy.

“You need to make sure you're articulati­ng what your next move is when it comes to the Green Line and how there's still a return on investment for Calgarians for a project of this magnitude,” she said. “We need to see more numbers and need to be able to communicat­e that to Calgarians on the risk analysis and what this project will look like.”

Mayor Jyoti Gondek said the project's transparen­cy is highlighte­d in the quarterly reports the Green Line board presents to council, and that the next update in June should reveal more clarity on whether the Green Line needs a revised scope or budget.

“If there's an additional ask that is needed, this is something that we're obviously going to discuss with provincial and federal partners as well,” she said.

 ?? JIM WELLS ?? Danilo Lora attends school in the Ramsay neighbourh­ood, where constructi­on continues on the Green Line LRT. Lora said having a station nearby would be “super convenient,” but as costs escalate, councillor­s are being warned they may need to reconsider the scope of the project.
JIM WELLS Danilo Lora attends school in the Ramsay neighbourh­ood, where constructi­on continues on the Green Line LRT. Lora said having a station nearby would be “super convenient,” but as costs escalate, councillor­s are being warned they may need to reconsider the scope of the project.
 ?? DARREN MAKOWICHUK ?? Constructi­on for the Green Line LRT continues at the Eau Claire Market on Tuesday. Crews are expected to start demolishin­g the market this summer.
DARREN MAKOWICHUK Constructi­on for the Green Line LRT continues at the Eau Claire Market on Tuesday. Crews are expected to start demolishin­g the market this summer.

Newspapers in English

Newspapers from Canada