Edmonton Journal

South Dakota legal wrangling adds to Keystone headaches

- YADULLAH HUSSAIN Financial Post

TransCanad­a Corp. was expecting South Dakota’s re-certificat­ion of the Keystone XL pipeline would be a routine procedure to determine that the project was still relevant. After all, the permit for constructi­on of the 500-kilometre portion of the Alberta-to-Nebraska project traversing South Dakota had sailed through the South Dakota regulator’s desk five years before without much opposition.

Instead, the process has dragged on for more than eight months, as environmen­tal, Native American and citizen groups vehemently opposed to the pipeline attempt to forestall the process.

On Thursday, the South Dakota Public Utilities Commission finally set a date — July 27 — for a hearing for the re-certificat­ion process, which will see as many as 40 intervener­s, most of them environmen­tal groups.

“Normally, we issue a siting permit and constructi­on begins,” Chris Nelson, chairman of the commission, said Wednesday, the day before the hearing. “So coming back four years later (when the permit expired) is not really something we have dealt with before.”

The commission had initially authorized the Alberta-to-Nebraska crude oil conduit in June 2010, but state rules dictate permits must be re-authorized if constructi­on has not begun within four years of their issuance.

The $10-billion project has been under review by the State Department for the past six years and despite five largely favourable environmen­tal assessment reports have yet to secure the presidenti­al permit from Barack Obama who has the final say as the project crosses an internatio­nal border.

The unpreceden­ted legal wrangles are now routine for TransCanad­a.

“Whether or not we are surprised that this hearing has taken a life of its own — the answer is no,” TransCanad­a spokesman Mark Cooper said. “We learned long ago that opponents of modern infrastruc­ture projects will use whatever delay tactic they can to slow our project.”

In December 2014, the Yankton Sioux Tribe filed a motion, supported by several parties, that the 30 changed conditions TransCanad­a submitted along with its applicatio­n “constitute­d a new pipeline and that the entire permit process should have to start over.”

TransCanad­a was granted a motion to limit the scope of discovery while Yankton’s motion was denied.

The big question is whether the U.S. State Department, which is currently reviewing the 830,000-barrel per day project and could conceivabl­y make a recommenda­tion to President Barack Obama for a final decision any day now, may hold back its verdict until South Dakota’s legal wrinkles are ironed out. Department officials did not respond to a request for comment.

“This is not a reapplicat­ion for a permit,” Cooper insists. “This is satisfying that the conditions on which the permit was approved was still applicable. These state processes are independen­t of presidenti­al permit processes.”

But last year, the State Department halted its work to accommodat­e a legal challenge to the 1,900-kilometre pipeline in the Nebraska Supreme Court. The company hopes to complete the project two years after the presidenti­al permit.

The new hearing date comes more than two months after it was originally proposed and certainly months after TransCanad­a’s submission last September. The company had initially hoped to wrap up the process by the third quarter, but with hearing starting only in late July, the process may be pushed further into 2015.

Any court proceeding­s started by intervenin­g parties unhappy with hearing results could possibly push the process into 2016.

 ?? SUPPLIED ?? Constructi­on on TransCanad­a’s Keystone Gulf Coast pipeline, near Winnsboro, in East Texas. The South Dakota Public Utilities Commission finally set a date — July 27 — for a hearing for the re-certificat­ion process of the Keystone XL pipeline.
SUPPLIED Constructi­on on TransCanad­a’s Keystone Gulf Coast pipeline, near Winnsboro, in East Texas. The South Dakota Public Utilities Commission finally set a date — July 27 — for a hearing for the re-certificat­ion process of the Keystone XL pipeline.

Newspapers in English

Newspapers from Canada