Journal Pioneer

Stone by stone

Parks Canada gives update on state of Province House renovation­s

- BY MITCH MACDONALD

A restored Province House may include more of P.E.I. than planners originally hoped for. During a presentati­on Monday night, Greg Shaw, the Parks Canada project leader for the major restoratio­n, said a stone conservato­r was previously unable to find a reliable source of Island sandstone for the interior of the National Historic Site.

While plans were made to use stone from New Brunswick, as well as a shipment ordered from the U.K., Shaw said provincial road engineers later found a quarry in Kelly’s Cross with hard sandstone. “They were amazed at the stone they found out there. We don’t have all of the tests back… but it’s looking promising,” Shaw told a crowd during a project update at Beaconsfie­ld Carriage House. “We’ll know more by mid-month, but right now it’s looking very, very promising that we’ll be able to use interior Island stone.”

The Province House update was the first of four presentati­ons in the Institute for Architectu­ral Studies and Conservati­on’s annual January lecture series.

Kristina Pompura, an architect and project manager with Parks Canada based out of Montreal, said staff searched all over Canada for stones with similar hardness and absorption characteri­stics of P.E.I. sandstone but could never find a match.

“Then this occurred, and it would be wonderful (if it works) because it will be completely compatible,” she said. “We’re hoping the remaining sandstone will be locally sourced.”

Reinstatin­g the interior is part of the massive project’s Phase 3, which is currently in the planning stage. Shaw said the design of

Phase 3 is expected to be complete by this fall, with work commencing in the winter. The cost for the project up to this point remains at about $61 million for the first two phases but is expected to go up once the planning for Phase 3 is determined.

The end of Phase 3, expected to be sometime in 2021, will also mark the completion of the project. Pompura is in the province this week for masonry mock-ups as part of Phase 2, which includes exterior improvemen­ts. Pompura said the mason has to

provide a series of mock-ups for the work they’ll be doing, such as laser cleaning, dismantlin­g and reinstalli­ng the stone.

“It’s almost like a series of tests and it’s going to happen over the next couple of weeks,” she said.

Phase 2 will continue into 2020. The earlier Phase 1, which included site stabilizat­ion and preparatio­n, was completed in April 2018.

Other news since the project’s last major update in June included awarding the roof stripping, roof truss and masonry contracts. A temporary waterproof membrane

has been placed over the roof for the winter, while modificati­ons were also made to the large, temporary exoskeleto­n that has helped stabilize the building and provide contractor­s with a work platform.

Shaw said finding a local source of sandstone was one of several “good news” pieces that have been found throughout the project. In fact, when Parks Canada began the project it was expected the entire building would have to be disassembl­ed and put back together. “We found that was not the case and we were able to do ‘in situ’

repairs,” said Shaw. “When you start investigat­ing, sometimes you find good things and not just bad things.”

Pompura also said the “ship has turned around considerab­ly” in regard to initial expectatio­ns of what the project would require.

She said the quality of the work done by the original masons who built Province House means contractor­s can now replace and repair where required, which means minimum interventi­on and preserving more of the building’s heritage.

 ?? MITCH MACDONALD/SALTWIRE NETWORK ?? Kristina Pompura, an architect and project manager with Parks Canada, and Greg Shaw, Parks Canada project leader for the Province House restoratio­n, are shown following a presentati­on to the Institute for Architectu­ral Studies and Conservati­on at Beaconsfie­ld Monday. The two provided an update on the state of the Province House restoratio­n.
MITCH MACDONALD/SALTWIRE NETWORK Kristina Pompura, an architect and project manager with Parks Canada, and Greg Shaw, Parks Canada project leader for the Province House restoratio­n, are shown following a presentati­on to the Institute for Architectu­ral Studies and Conservati­on at Beaconsfie­ld Monday. The two provided an update on the state of the Province House restoratio­n.

Newspapers in English

Newspapers from Canada