Work begins to service land for new Canadian Tire developmen­t

- Moose Jaw Express staff

Servicing of land for the new Canadian Tire developmen­t at 250 Thatcher Drive East has begun. Contractor KMS Constructi­on plans to install sewer, storm and water main pipes to the site, with constructi­on expected to be finished by June 15, weather permitting, according to a news release. City hall is encouragin­g motorists to obey all traffic signs and exercise caution for everyone’s safety.

Canadian Tire Real Estate Limited (CTREL) paid the municipali­ty a non-refundable deposit of $250,000 in January as part of an agreement to purchase property near the Moose Jaw Exhibition Company site. The deal includes 11.95 acres (4.78 hectares) for $3,171,725, or $265,500 per acre. The property is in the southeast corner near Thatcher Drive East.

As per the agreement with CTREL, city hall will service the land sold to Canadian Tire and complete a partial infrastruc­ture connection to 8.56 hectares (21.4 acres) north of the property for potential future developmen­t. The municipali­ty has not yet announced any developmen­ts for that piece of land. However, clauses in the deal give CTREL firm control for decades over what can be built there.

The original contract between the city and CTREL was to close on April 16, 2020, and Canadian Tire had to commence constructi­on before Oct. 31, 2021. However, based on a renegotiat­ed contract, the company must start building before Oct. 31, 2022. This means the new building — which would bring Canadian Tire, Mark’s and SportChek under one roof — could be open by 2023.

 ??  ?? Work has begun on the north side of Thatcher Drive to service the proposed Canadian Tire developmen­t. This view looks west. (Photo by Jason G. Antonio)
Work has begun on the north side of Thatcher Drive to service the proposed Canadian Tire developmen­t. This view looks west. (Photo by Jason G. Antonio)