National Post

Why most aren’t shocked by subway extension screwups

- Chris Selley Comment from Toronto cselley@nationalpo­st.com Twitter.com/cselley

“Look over there!” TTC CEO Andy Byford pointed and shouted to reporters aboard a chartered city bus early Friday afternoon. He was jokingly averting our eyes from a disabled TTC bus being towed away. But it was basically what he had been doing in earnest all morning, as he and site manager Peter Boyce toured us around York University station, midway point on the late and overbudget six-stop Toronto-York Spadina Subway Extension ( TYSSE).

What we saw was a loud, muddy, freezing- cold constructi­on site, but one in which an objectivel­y impressive subway station — if you like that sort of thing — is taking shape. It has a nifty wavy roof. It has a grand entrance through which natural light will filter down to the platform. Passengers will ostensibly look up and marvel at the “waffle slab” concrete roof.

All very nice, but we were there because of bad news. As we bused northward, the project officially got considerab­ly more expensive: A staff report anticipate­s up to $400-million extra will be needed to settle what Byford says are routine disputes with contractor­s — 60 per cent to be borne by the city and 40 per cent by York Region. That brings the total price to around $ 3.2 billion for a subway line scheduled to open by the end of 2017 — a significan­t departure from an original budget of $ 2.6 billion and an original deadline of 2015.

Few Torontonia­ns will be shocked. Byford, however, would like them to look on the bright side. “The good news is, the TYSSE is 80-percent complete. The track is virtually all in, the tunnels were completed back in 2013, the six stations are well advanced,” he told the cameras after the media tour. “So the end date of December 2017 remains on track.”

At one point, after all, staff told him it might be 2019. At that point he cleaned house and brought in civil engineerin­g firm Bechtel to reorganize project management. It could be worse.

By the end of our threehour tour, Byford had said “but at least you’re getting a great subway” so many times in so many different ways, and had shifted blame to so many third parties — previous TTC commission­ers, the Ministry of Labour, contractor­s — that it was getting a bit much. Subtle message management this was not. On the other hand, he makes a compelling case that he inherited a heritage- breed turkey when he took the job in 2012, and has made the best of it.

This is i n many ways a classic Toronto transit screwup, beginning with the fact the budget was set before the project had been designed — which was the most basic finding of a 2010 report into the legendary debacle of the St. Clair streetcar right- of- way, incidental­ly. To take just one maddening example: The TTC proposed modest stations, not unlike those on the Sheppard line — “fit for purpose,” as Byford put it, the purpose being to move people from Point A to Point B. Politician­s decided they wanted to think bigger, so the TTC commission­ed some architectu­ral landmarks. “No, no, that’s too big,” the politician­s demurred, and we got halfway bold designs instead.

That sort of dithering costs time and money. How could it not? And it’s not the TTC’s fault the Ministry of Labour shut down the York University site for an unconscion­able six months after the death of a worker there in 2011.

Still, t he problem remains: Not without cause, the TTC has a lousy reput ation as a deliverer of on- t i me, on- budget projects. And as Mayor John Tory has often observed, that reputation is a significan­t obstacle for would- be city builders to overcome: Metro Vancouver’s referendum on a $ 7.5- billion suite of transporta­tion projects failed in large part because TransLink, the regional authority, suffered from similar criticisms.

Asked how we might avoid trust- eroding sticker shocks like this in the future, Byford pointed to the multiple-contractor “design-bid-build” model the TTC adopted for the TYSSE, as opposed to the “design- build” option it rejected. “Design- build buys you t hat certainty because any cost overrun would typically be at the risk of the contractor,” he said. “The balance, though, is that you often pay extra to get that certainty.”

“Paying more” is somet hing Torontonia­ns are used to. “Paying more or less what they said it would cost” would potentiall­y be a very productive novelty. As Byford says, there are important lessons to be learned here for the TTC.

We must hope its political masters are willing to learn them as well.

A COMPELLING CASE THAT HE INHERITED A HERITAGE-BREED TURKEY WHEN HE TOOK THE JOB IN 2012. — SELLEY THE BUDGET WAS SET BEFORE THE PROJECT DESIGNED.

 ??  ??

Newspapers in English

Newspapers from Canada