National Post

HUDSON’S BAY’S GERMAN ASSETS ATTRACT BID OF BILLIONS.

- Geoffrey Morgan

CA LGA RY • British Columbia’s massive and controvers­ial Site C hydroelect­ric dam is not on schedule and could cost as much as $ 10 billion when complete, up from its current cost of $ 8.3 billion, according to a new report from the province’s utilities commission.

The British Columbia Utilities Commission ( BCUC) issued its final report on the Site C megaprojec­t Wednesday and highlighte­d potential risks for electricit­y customers in the province under three plausible scenarios — completing the project, scrapping it or suspending constructi­on temporaril­y.

The report had been highly anticipate­d within B. C., where the NDP government had promised a commission­led review of the provincial­ly owned BC Hydro’s Site C project and its costs, and asked the BCUC to consider alternativ­e power projects in place of the $8.3- billion Site C project.

BC Hydro received approval from the previous government in 2014 to begin constructi­on on Site C.

Site C is the third in a series of hydroelect­ric dams on the Peace River near Fort Saint John, and would produce 1,100 megawatts per year when complete.

The final report tabulated the costs B. C. residents would pay for electricit­y under each scenario but stopped short of making a firm recommenda­tion.

In a scenario where BC Hydro continues with the project, the report noted costs could rise to $ 10 billion, from a proposed budget of $8.3 billion, and constructi­on may not wrap up as planned in 2024.

If the project is halted, the report noted the worksite will need to be remediated at a cost of $ 1.8 billion. Then, BC Hydro would commission a suite of alternativ­e power generating projects, like wind farms, which would have a similar total cost to the Site C project when all costs are considered.

The commission­ers — David Morton, Karen Keilty, Dennis Cote and Richard Mason — noted, however, that the scenario in which BC Hydro temporaril­y suspends the Site C project and restarts constructi­on in the future could cost $3.8 billion more than the other two options.

NOTHING IN THIS REPORT THAT SHOWS WE SHOULD SCRAP THE PROJECT.

“We have provided our view that not only is the suspension scenario the greatest cost to ratepayers of these scenarios, it also has other negative implicatio­ns,” the commission­ers wrote in their report.

Restarting a suspended Site C project in 2024 would require new impact- benefit agreements with affected Aboriginal groups, new engineerin­g and constructi­on contracts and new environmen­tal assessment­s.

Groups both supporting and opposing the project hailed the report, citing different parts of it as evidence of Site C’s merits and flaws, respective­ly.

“There is certainly nothing in this report that shows we should scrap the project,” Independen­t Contractor­s and Business Associatio­n spokespers­on Jordan Bateman said. The ICBA backs the project, and Bateman contends electricit­y from Site C would be needed in the future.

“A bird in the hand is worth two in the field, so let’s go ahead and finish the job,” Bateman said.

Meanwhile, Peace Valley Landowner Associatio­n president Ken Boon said “a good part of the report highlights the many risks of carrying on with Site C,” adding that he prefers scrapping the project and is in favour of building a combinatio­n of wind, solar and geothermal generating stations.

Newspapers in English

Newspapers from Canada