National Post

‘I am really puzzled’

Collapse shines harsh light on ABC technique

- Jason Dearen

As the 950- tonne concrete bridge section was swung into place over a highway last weekend, Florida Internatio­nal University officials were beaming with pride.

The pedestrian bridge on the edge of the Miamiarea campus was a signature achievemen­t of the school’s Accelerate­d Bridge Constructi­on University Transporta­tion Center, a research group set up with federal funding a few years ago to show how spans could be built faster and cheaper in the U.S.

“FIU is about building bridges and student safety. This project accomplish­es our mission beautifull­y,” FIU President Mark B. Rosenberg boasted that day.

‘ “We are filled with pride and satisfacti­on at seeing this engineerin­g feat come to life and connect our campus to the surroundin­g community.”

Five days later, the bridge collapsed onto the busy sixlane highway, crushing cars and killing at least six people in a tragedy now under federal investigat­ion.

While it’s not yet clear what caused the failure of the unfinished span Thursday, the disaster has cast a spotlight on a rapid constructi­on technique widely used around the U.S.

Accelerate­d bridge constructi­on, or ABC, involves assembling large sections of a span offsite, then moving the massive pieces into place all at once.

The technique eliminates the lengthy road closings and other traffic disruption­s that can result when a bridge is built out over a highway piece by piece. It is also considered by some engineers to be safer for hard hat workers and motorists because much of the constructi­on isn’t done in the middle of traffic.

The general approach has been around since the mid19th century — and has been used safely and successful­ly for a long time — but interest in ABC has increased in recent years as states have looked for quicker, less expensive ways to replace thousands of aging bridges.

In the case of the Florida tragedy, engineerin­g experts said the question is where was the fatal mistake: in the design of the bridge, in the way its constructi­on was carried out or in the materials used?

To some bridge engineers, the decision to install the span’s main concrete segment over a busy road before building its main support tower was puzzling. Traditiona­lly, the tower is con- structed first, and the walkway or roadway is anchored to it with cables.

“It ’s odd,” said Henr y Petroski, a professor of civil engineerin­g at Duke University and a leading authority on engineerin­g failures. “That’s probably why they used t his so- called ABC method, so they could get the span over the roadway in one operation, because if you do it incrementa­lly, you have to interrupt traffic.”

Investigat­ors will also be looking at the companies building the project, a collaborat­ion between MCM Constructi­on, a Miami-based contractor, and Figg Bridge Design, based in Tallahasse­e. Both companies have been involved in constructi­on accidents before.

FIGG was fined in 2012 after a section of a bridge it was building in Virginia fell and injured several workers. Virginia’s labour department later fined Figg for constructi­on violations, and a subcontrac­tor sued accusing the firm of negligence and poor design. MCM was accused of substandar­d work in a lawsuit filed this month by a worker injured when a makeshift bridge the company built at the Fort Lauderdale airport collapsed under his weight.

Professor Amjad Aref, a researcher at the University at Buffalo’s department of civil, structural and environmen­tal engineerin­g, said it is unclear what the builders at FIU were using in lieu of a tower to support the segment that collapsed.

The span had some kind of cables to help support it, and the bridge section that collapsed was attached to two smaller pylons at either end.

But in ABC projects like the FIU span, the loss of the extra support from the main tower during constructi­on is a risk, he said.

“Until all the pieces are put together to transmit the loads safely to the foundation­s, these bridges may suffer disproport­ionate or full collapse due to instabilit­y,” Aref said.

“Typically, this process requires a few weeks. During that time, they are often supported by another system to ensure stability because they are really vulnerable to collapsing.”

“I am really puzzled that the tower does not exist,” Aref said.

Engineers say the method has been used safely in other projects for years, and in general keeps the public safer. “What really bothers me is with ABC, the benefits are so substantia­l that I would hate to see this accident lead to its reduced use,” said Michael Culmo, a bridge engineer in Connecticu­t who has worked on accelerate­d constructi­on projects for decades. “While this is a tragedy, the process itself is very safe.”

 ?? PEDRO PORTAL / THE MIAMI HERALD VIA AP ?? The pedestrian bridge that collapsed in Florida was built using a rapid constructi­on technique known as ABC that eliminates lengthy road closures and other disruption­s.
PEDRO PORTAL / THE MIAMI HERALD VIA AP The pedestrian bridge that collapsed in Florida was built using a rapid constructi­on technique known as ABC that eliminates lengthy road closures and other disruption­s.

Newspapers in English

Newspapers from Canada