National Post

Oil shippers seek clarity on Trans Mountain costs

Companies fear tolls linked to rising price tag

- Amanda Stephenson

• A group of oil shippers is asking the Canada Energy Regulator to compel the company behind the Trans Mountain pipeline expansion to provide them with a full and detailed breakdown of the project’s escalating constructi­on costs.

The shippers — which includes Canadian Natural Resources Ltd., Suncor Energy Inc., Cenovus Energy Inc., Petrochina Canada Ltd. and Marathon Petroleum Canada — are seeking an order from the regulator requiring Trans Mountain Corp. to provide more informatio­n about why the project’s costs have ballooned to more than $30 billion from a 2017 estimate of $7.4 billion.

“The stakes are high: billions of dollars at issue, with Trans Mountain’s (costs) having more than quintupled since 2017 — and its costs are still growing by billions, seemingly unchecked,” the oil companies stated in a motion filed with the Canada Energy Regulator earlier this week. “Yet Trans Mountain refused to answer most of participat­ing shippers’ (request for informatio­n) and inappropri­ately dismissed most requests as irrelevant ‘fishing expedition­s.’ ”

The pipeline, which was bought by the federal government in 2018, is Canada’s only oil pipeline to the West Coast. Its nearly complete expansion project will boost the pipeline’s capacity by 590,000 barrels a day to a total of 890,000 barrels a day, improving access to export markets for oil companies.

But Trans Mountain and its oil company customers are currently engaged in a dispute over tolls, the term for the fees the pipeline company will charge to ship oil on the expanded pipeline.

In its most recent update provided last month, Trans Mountain said it now has reason to believe the costs of the project will come in roughly $3.1 billion higher than the $30.9 billion estimate in May 2023. It said a final tally won’t be available until after the project’s completion, expected sometime this spring.

Oil companies are concerned with the escalating costs because they will have to pay for a portion of them in the form of rising tolls.

While around 70 per cent of the project’s cost overruns will be borne by Trans Mountain, the remaining third — more than $9 billion — is considered “uncapped costs,” which increase tolls in accordance with a formula agreed to by shippers and approved by the regulator more than a decade ago.

But the oil shippers say the new benchmark toll Trans Mountain wishes to charge is nearly twice the amount of a 2017 estimate, and say more informatio­n is needed to prove the rising price tag of the project is both reasonable and necessary. They say they have asked Trans Mountain to provide a more detailed breakdown, and are seeking an order from the regulator because they aren’t satisfied with the company’s response.

The Canada Energy Regulator has already granted approval for Trans Mountain to charge the higher toll on an interim basis, but is yet to make a final decision.

For its part, Trans Mountain — which is a Crown corporatio­n — has said 70 per cent of the project’s cost overruns will be borne by the pipeline company and will have no effect on tolls.

The company has also previously stated that because of the project’s cost overruns, it expects only “modest returns” on its investment in the first few years of the expanded pipeline’s operation. It says any toll level below what Trans Mountain has applied for “could impact Trans Mountain’s ability to meet its financial obligation­s.”

In December, Trans Mountain submitted written evidence to the regulator in which it said the expansion project has been affected by “extraordin­ary” factors that include evolving compliance requiremen­ts, Indigenous accommodat­ions, stakeholde­r engagement and compensati­on requiremen­ts, extreme weather and the pandemic.

The company said in its filing that the project’s cost overruns were “reasonably and justifiabl­y incurred.”

 ?? JASON FRANSON / THE CANADIAN PRESS FILES ?? In an update last month on its pipeline expansion, Trans Mountain Corp. said it expects the bill for the project to be $3.1 billion higher than its $30.9 billion estimate last May. The project was forecast to cost $7.4 billion in 2017.
JASON FRANSON / THE CANADIAN PRESS FILES In an update last month on its pipeline expansion, Trans Mountain Corp. said it expects the bill for the project to be $3.1 billion higher than its $30.9 billion estimate last May. The project was forecast to cost $7.4 billion in 2017.

Newspapers in English

Newspapers from Canada