Ottawa Citizen

Inspection­s revealed faulty LRT concrete

O-Train boss says contractor’s quality control system is working

- JON WILLING

Inspectors have found a range of problems with concrete work at the city’s LRT sites, according to newly released inspection reports that offer a behind-the-scenes look at Ottawa’s biggest infrastruc­ture project.

The problems relate to concrete pours at worksites such as unacceptab­le temperatur­es and missed durability tests, and have forced contractor­s to sometimes redo work or come up with workaround­s.

The city finally released the 63 reports to Ken Rubin after he successful­ly convinced a provincial adjudicato­r that the records are of public interest. Rubin, an Ottawa access-to-informatio­n specialist, was originally stymied by the Rideau Transit Group, which didn’t want the city-held records released. The city, which agreed with Rubin that releasing the records wouldn’t cause harm to RTG, has the documents since RTG is its main contractor on the $2.1-billion LRT project.

The 644 pages of non-conformanc­e reports largely detail deficienci­es with concrete pouring activities around the maintenanc­e and storage facility, stations and in the downtown tunnel.

All of the inspection­s were initiated by the constructi­on contractor’s quality control team, making sure work completed by the subcontrac­tors meets the city’s requiremen­ts and the RTG design. Non-conformanc­e reports are standard documents in the constructi­on industry, helping contractor­s and clients make sure the quality of work is up to snuff. They make sure the client — in this case the City of Ottawa — is getting the safe transit infrastruc­ture it paid for.

There’s a huge amount of concrete going into the constructi­on of the Confederat­ion Line. The 2.5-kilometre tunnel alone is expected to have been built with 84,181 cubic metres of poured concrete when the work is done.

Several of the 63 released nonconform­ance reports signal deficienci­es in concrete work.

After one concrete pour in the tunnel early in 2016, an inspector learned a load of concrete didn’t conform to the mix design, “causing significan­t damage to the running tunnel arch” in one area. An engineer told the builder to remove and replace the deficient concrete.

One report, generated after an inspection of Lyon station in July 2016, detailed an insufficie­nt amount of concrete poured in three arches. According to the report, the concrete placement “was stopped due to concern of bulkhead failure after workers reported hearing timber cracking under the pressure of the concrete.” The builder indicated the bulkhead design would be reinforced.

The concrete must meet the city’s standards and contractor’s specificat­ions if it’s going to be poured.

In June 2016, workers at Blair station added water to a concrete mix after more than half of the mix was discharged, leading to a nonconform­ance report.

That report is particular­ly eyeopening.

Maria Anna Polak, a professor in the civil and environmen­tal engineerin­g department at the University of Waterloo, said adding water to a concrete batch at the worksite is “an absolute no-no.”

“If you add extra water, this extra water contribute­s to lower strength. It contribute­s also to shrinkage, which means basically when the concrete hardens, it cracks,” Polak said in an interview.

In this case, the concrete was used as is. The contractor made sure the concrete passed the durability tests to satisfy the standards.

Durability tests are important parts of quality management and ultimately decide if the concrete is suitable.

On Sept. 14, 2015, 11 loads of concrete were delivered for workers to build a wall in the tunnel. A nonconform­ance report says seven of the loads poured didn’t meet the specificat­ions for the mix design — although strength tests on the concrete passed the requiremen­ts. The inspector who wrote the report told the contractor to test the concrete before pouring it and reject trucks that don’t meet the specificat­ions.

In December 2014, during a concrete pour of a wall at the access track to the maintenanc­e and storage facility, seven concrete trucks were rejected because the air content of the concrete was off. Four other trucks also exceeded the aircontent limit “and had to be used to avoid major pour interrupti­ons and cold joints,” a report says. The concrete used in the wall passed strength tests.

The temperatur­es of the concrete during the pouring and curing periods — the process by which the concrete is set — were also flagged in several of the non-conformanc­e reports. In most cases, inspectors directed the contractor to monitor the concrete for any cracking and make any necessary repairs.

In summer 2016, an inspector wrote up a deficiency report for off-temperatur­e concrete at an overpass, noting that the subcontrac­tor was warned about not having a temperatur­e-control plan. “However, they stated that temperatur­e would not be an issue,” the report says.

Some reports illustrate how the contractor wasn’t able to adapt quickly to Mother Nature.

The concrete curing temperatur­e for the new deck on the Booth Street bridge was out of whack during four unexpected­ly cool evenings in May 2016. There were reports that flagged concrete poured beyond a required time threshold for dischargin­g the mixture. In one report, the inspector noted that poured concrete was actually 23 minutes past the allowable time for pouring. Workers subsequent­ly repaired cracks and conducted a flood test on the structure.

A few cases of poor communicat­ion also resulted in non-conformanc­e reports.

An inspector found a cement contractor wasn’t testing the strength of the material, but the inspector also didn’t know a lab was onsite, taking tests during the pour. In another case, a technician missed testing the quality of concrete during a pour at Parliament station. There was miscommuni­cation between a field engineer and the quality-control team, a report says.

RTG answered questions by email relating to the concrete work on the LRT project but said it couldn’t speak to specific nonconform­ance reports because they’re considered “internal corporate documents.”

The company said it “maintains a rigorous quality management system” to meet the city’s expectatio­ns, provisions of the LRT contract and internatio­nal standards.

Asked specifical­ly about concrete that goes past prescribed time limits between producing and pouring, RTG said it’s normal that quality inspectors find issues related to the product or process.

“Given the logistics of delivering and placing large volumes of concrete it is inevitable, on any project, to have some loads exceed time limits,” RTG says. “There are options in those cases, one of which is to reject the load.”

Non-conformanc­e reports also warn about formwork — the mould for concrete — being removed too early during the curing period, wrongly installed reinforcin­g bars and deficienci­es on girders at the Hurdman station elevated guideway.

Questionab­le waterproof­ing is another common problem in the reports.

A report from 2015 noted missing strips of membrane in Parliament and Lyon stations. The supplier was told to follow the approved drawings.

Another report that year flagged a problem with a design-required redundant “waterstop” in a constructi­on joint at Lyon station. The work was allowed. The builder is “proceeding at their own risk of damage due to water infiltrati­on,” the report says.

At the connecting line to the maintenanc­e facility, an inspector found there was no waterproof­ing installed in areas that underwent emergency repair in 2015.

It’s in RTG’s interests to make sure the LRT system is built properly since the company also has a 30-year maintenanc­e contract from the city.

Steve Cripps, the city’s director of O -Train constructi­on, said the non-conformanc­e problems were raised by RTG’s constructi­on arm, Ottawa Light Rail Transit Constructo­rs, which shows the builder’s quality-management system is working.

“The city has reviewed the documentat­ion provided by the Ottawa Light Rail Transit Constructo­rs for each (non-conformanc­e report) and is satisfied that they have conducted the appropriat­e due diligence,” Cripps said in an email.

The builder is scheduled to deliver the LRT system to the city by Nov. 2. It’s the second deadline after RTG couldn’t meet the previous May 2018 delivery date. The city plans to have the rail line open to passengers by the end of November, but it should have a better idea by the end of the summer if RTG will meet the new deadline.

 ?? CITY OF OTTAWA LRT ?? In one case, a technician missed testing the quality of concrete during a pour at Parliament station, shown here during its excavation in 2016.
CITY OF OTTAWA LRT In one case, a technician missed testing the quality of concrete during a pour at Parliament station, shown here during its excavation in 2016.
 ?? PHOTOS: CITY OF OTTAWA ?? It’s in RTG’s interest to make sure the LRT is built well as the company has a 30-year maintenanc­e contract with the city.
PHOTOS: CITY OF OTTAWA It’s in RTG’s interest to make sure the LRT is built well as the company has a 30-year maintenanc­e contract with the city.
 ??  ?? Workers pour concrete caissons north of the existing Hurdman Station for the LRT project.
Workers pour concrete caissons north of the existing Hurdman Station for the LRT project.
 ??  ?? Crews form the stairs at Blair Station.
Crews form the stairs at Blair Station.

Newspapers in English

Newspapers from Canada