Ottawa Citizen

FAILING LRT GRADES

City inspectors find flaws

- JON WILLING

Parts of Ottawa’s $2.1-billion LRT project failed inspection­s by city building inspectors, who walked away unsatisfie­d by some of the work they saw at constructi­on sites.

Many of the failed inspection­s between Jan. 1, 2015, and Sept. 20, 2017, were related to plumbing and fire safety, according to more than 400 reports reviewed by this newspaper through an access-toinformat­ion request.

Inspectors reviewed various parts of the constructi­on, such as mechanical, plumbing, foundation and fire safety, and wrote an assessment for each inspected element.

The large majority of the inspection­s were listed as progress inspection­s or inspection­s that resulted in passing grades.

However, there were 63 times when an inspector recorded a “fail” and called for a re-inspection of a constructe­d element.

Interested in the quality of constructi­on on the Confederat­ion Line, this newspaper initially filed the request for informatio­n on Sept. 20, 2017; about 10 months later, the city signed off on the release of the inspection reports. The reports provide a glimpse into the quality of work on the city’s largest-ever infrastruc­ture project, to which all three levels of government have contribute­d significan­t public funds.

The city announced this week another delay in the completion of the LRT project.

It’s not expected to be ready for customers until the first quarter of 2019, instead of the promised November 2018 launch.

Rideau Transit Group, the consortium building the Confederat­ion Line, has an internal qualitycon­trol system designed to catch any faults in constructi­on. When there is a mistake, it’s recorded in a “non-conformanc­e report,” the fix is made, or the issue is accepted if there isn’t a major problem, and the file is reviewed by the city. Nonconform­ance reports are standard in the constructi­on industry and the LRT project has produced many, such as those related to concrete.

However, the city itself has its own inspection requiremen­ts under the Ontario Building Code. A team of inspectors working for the city is tasked with making sure elements of the LRT system, like all other constructi­on projects in Ottawa, are built to standards under provincial law.

John Buck, the city ’s manager of building inspection and enforcemen­t, estimated that his staff have completed between 1,100 and 1,200 inspection­s of the LRT system. The reports viewed by the Citizen reveal only a snapshot of that work. Four out of the city’s roughly 50 to 55 field inspectors are dedicated to the LRT project. Under the building code, the inspectors are required to complete an inspection within 48 hours of a request by a contractor, but the city strives to respond sooner, Buck said.

It can consume precious time when inspectors have to return to any job site to recheck pieces of constructi­on that generated failed inspection­s.

“Can it be frustratin­g ? Absolutely,” Buck said, but he added that it’s just part of the building process.

“It’s our jobs to look critically and raise these deficienci­es.”

The reports illustrate the problems inspectors have found at LRT work sites.

An inspector recorded a fail in April 2017 after reviewing plumbing in the downtown tunnel and learning that about 60 vertical sanitary and stormwater pipe locations had blockages.

When an inspector reviewed the roughed-in plumbing work at the u Ottawa station in August 2016, he also recorded a fail, noting that several tasks still needed to be completed before the concrete pour, such as ensuring the pipes had the right slope and pressure.

An inspection of plumbing around Lyon station in the first half of 2017 reported damage to the weeping tile from concrete and reinforcin­g steel. Inspection­s related to the same building permit flagged the need to prevent sand and grit from entering the plumbing system and the need for a control valve on the station.

At Blair station in May 2016, an inspector recorded a failed inspection after reviewing the piping in a mechanical room.

Inspectors are also tasked with reviewing fire-protection measures.

There was a failed inspection at Rideau station in October 2017 because the walls around an escalator weren’t being built to have fire separation, which prevents the spread of fire.

In September 2017, an inspector recorded a fail because a sprinkler line wasn’t installed properly at Hurdman station.

During another inspection in December 2015, an inspector wasn’t able to verify that the fire-detection system worked at St. Laurent station.

An inspection of the fire-stopping and fire-separation infrastruc­ture also failed in June 2015 at the maintenanc­e and storage facility.

An inspector filed a failed inspection at the train-storage facility on Belfast Road in March 2016 after noticing problems with the firesuppre­ssion system and a lack of documentat­ion.

There were also failed inspection­s when it came to excavation­s.

After an inspection at the u Ottawa station in February 2017, an inspector recorded a fail after learning an excavation and foundation were completed without a city inspection, requiring the builder to produce several reports on the work. A similar failed inspection happened in January 2017 at St. Laurent station, with the inspector asking for documents after the contractor had already finished the excavation and foundation.

Inspectors have also run into challenges trying to do their jobs.

One inspector noted in a November 2015 report that he wasn’t allowed to take a picture of a catwalk in the maintenanc­e and storage building “due to security reason.”

(Alstom, the LRT vehicle provider, has previously restricted access to the facility to prevent the disclosure of its vehicle-building techniques.)

Failed inspection­s are sometimes logged for reasons not necessaril­y related to the infrastruc­ture itself.

A report in September 2017 says a site meeting was requested by the contractor at the storage facility on Belfast Road, but that no one was available at the site. The contractor didn’t answer his phone.

RTG community liaison officer Conrad McCallum sent an emailed response to questions on behalf of the company. RTG was asked for an explanatio­n for inspection­s that fail and whether the company has been requesting inspection­s too early in the constructi­on process.

“RTG has requested interim inspection­s during the course of constructi­on to provide documentat­ion and access for visual inspection to prove conformanc­e to (Ontario Building Code) requiremen­ts,” the company says.

“This is an example of best practices in regards to open and transparen­t communicat­ion with our city building department. RTG and (the building code services branch) have been working collective­ly to conduct timely inspection­s during the course of the project as a project delivery method to achieve occupancy.”

Building inspectors have been “very accommodat­ing ” in working with RTG during the LRT constructi­on, the company says.

“The (LRT) project has multiple phases and activities that require building code consultati­on and approval,” RTG says. “The city’s building code inspectors have been proactive in this exercise and RTG will continue to work conjointly with the building code services branch through the inspection process in the final phase of the project.”

Properly building transit infrastruc­ture is in RTG’s interests since the company ’s maintenanc­e arm is contracted to maintain the rail system, including the Stage 2 Confederat­ion Line expansion, until 2048.

Alan Shaw, the chief building official in Sarnia and the immediate past president of the Ontario Building Officials Associatio­n, said finding deficienci­es in constructi­on is very common, which means failed inspection­s aren’t unusual.

“The primary reason a building inspector would fail a project is because they don’t want you to proceed with other things before you get this right,” Shaw said, adding that “to fail an inspection is not the end of the world.”

If there were perfectly built projects all the time, there wouldn’t be a need for building code inspectors, Shaw said.

“We’re there to catch the stuff that other people miss,” he said.

In Ottawa, Buck said the city’s team of building inspectors is short-staffed by about 10 to 15 per cent. The city is trying to recruit new inspectors in a competitiv­e market. Later this month, council is scheduled to consider a proposal to spend $1 million to hire 12 more staff in the building code services branch.

The branch’s workload will only grow as the city embarks on the Stage 2 expansion in 2019.

“It has taxed our resources somewhat,” Buck said of Stage 1. “We’ve also spent many years on office work even before constructi­on got underway on the permitting side.”

The team of four inspectors are committed to making sure the LRT system is constructe­d according to the law, Buck said.

“They’re invested and they’re proud of their work,” Buck said. “They feel its very critical to the city and the project.”

 ??  ??
 ?? TONY CALDWELL ?? LRT CONFEDErAt­ION LINE CONstruCtI­ON ON QuEEN StrEEt IN OttAwA ON MONDAy.
TONY CALDWELL LRT CONFEDErAt­ION LINE CONstruCtI­ON ON QuEEN StrEEt IN OttAwA ON MONDAy.
 ?? ERROL MCGIHON ?? THE CyrvILLE StAtION ON tHE CONFEDErAt­ION LINE.
ERROL MCGIHON THE CyrvILLE StAtION ON tHE CONFEDErAt­ION LINE.

Newspapers in English

Newspapers from Canada