Penticton Herald

BRIDGE OUT

- By JOE FRIES

Say goodbye to the little bridge on Nanaimo Avenue East. Following the advice of staff and an engineerin­g firm, council voted unanimousl­y Tuesday to permanentl­y remove the 30-metre bridge when that stretch of Penticton Creek undergoes restoratio­n work that’s currently scheduled for 2024.

While the project is still years away, design work is underway now, but has been held up by questions about the bridge’s fate, according to Mitch Moroziuk, the city’s general manager.

As it exists today, the bottom of the bridge is 29 centimetre­s lower than required to handle a one-in-200-year flood event for which the municipali­ty has to prepare.

“The water will actually be pushing against the side of the bridge, and that creates a significan­t risk from a flood-protection view, because that bridge could actually be dislodged and then pushed into the stream, and that would then cause significan­t issues for the downstream people,” he explained.

If the bridge were left in place, continued Moroziuk, it would need $250,000 worth of work in the next five to 10 years, and would probably prevent the city from obtaining the permits required to work in the creek because the structure would remain a pinch point for flooding.

The alternativ­e, which council supported, will see the bridge removed to allow for expansion of the creek bed, and replaced with walking and cycling paths on both sides.

Once it’s gone, the closest non-vehicle crossing will be 335 metres away at Wade Avenue, while the closest vehicle bridge will be 407 metres away at Ellis Street, with additional crossings for cars at Vancouver and Eckhardt avenues.

Road realignmen­ts and a new left-turn lane at the intersecti­on of Pickering Street and Haven Hill Road will be required, said Moroziuk, “but it’s not expected there will be any significan­t impacts on traffic by taking that bridge out.”

Finally, he told council, fire Chief Larry Watkinson has confirmed response times to the area will increase by 32 to 35 seconds once the bridge is gone, but the new routing will still be manageable in case of emergencie­s.

Design work for that stretch of Penticton Creek — approximat­ely 300 metres upstream of the bridge — is being funded in part by a $159,000 grant from the South Okanagan Conservati­on Fund. The grant is flowing through the Penticton Flyfishers Club, and is being matched by the city.

The actual reconstruc­tion cost of that portion of the creek, which was identified as a priority in the 2018 Penticton Creek Master Plan, is pegged at $3.4 million. So far the city has lined up just a single $750,000 grant for the project.

The creek restoratio­n project began in 2013, and seeks to restore the creek's ability to support wild fish population­s, provide flood protection for the community and offer greenspace in the heart of the city.

To date, two separate projects, which replaced an aging concrete flume with more natural habitat, have been completed on the creek extending from Ellis Street about 200 metres upstream to Nanaimo Avenue. Restoring the entirety of Penticton Creek within the city is estimated to cost in the neighbourh­ood of $30 million.

 ?? JOE FRIES/Penticton Herald ?? The bridge across Penticton Creek at Nanaimo Avenue East is slated to be pulled out permanentl­y in 2024.
JOE FRIES/Penticton Herald The bridge across Penticton Creek at Nanaimo Avenue East is slated to be pulled out permanentl­y in 2024.

Newspapers in English

Newspapers from Canada