Regina Leader-Post

Delays the norm at Capital Pointe

26-storey project remains little more than a hole in the ground

- ASHLEY ROBINSON

First launched in 2005 and approved by Regina city council in 2010, Capital Pointe, a hotel-andcondo complex is to be the largest structure in the city at 26 stories.

At the time it was scheduled to be finished by 2012.

Seven years, numerous setbacks and several developers later it is a big hole at the corner of Albert Street and Victoria Avenue.

Fortress Real Developmen­ts Inc. who now handles the project, posted a July update on its website stating, “Despite the poor weather conditions in Regina during the spring and early summer, which made the excavation of the clay material at the Capital Pointe site even more difficult, the progress has continued.”

This spring and summer saw drought-like conditions grip Regina with less than half the normal amount of rain falling. When asked by the Leader-Post about “poor weather conditions” Fortress responded over email stating, “Weather conditions during the early part of the year were far from ideal for work of this nature, particular­ly given the soil conditions that are prevalent down at a four and five storey depth.”

In November Fortress held a press conference to update on the project. At the time Jawad Rathore, president and CEO of Fortress Real Developmen­ts, said the project was about five weeks behind schedule due to unexpected delays in excavating the foundation for the building. But he was confident the large crane used for building the foundation would be in place by January — it is still not in place.

When asked about the current status of the project Fortress said it is now three to four months behind schedule.

The constructi­on company has experience­d delays at the site due to ground condition and debris from previous buildings.

When the city was asked about the project over email Louise Folk, director of developmen­t services said, Fortress was issued a permit for excavation and shoring in September, 2015 and had six months to begin constructi­on with two years to finish constructi­on.

As well, Folk said same as all constructi­on projects the city is inspecting the site on a regular basis and following up with the developer about constructi­on progress, site conditions and public safety.

Next door to the Capital Pointe project, at Bregg Cleaners & Tailors, owner Terry Thorsteins­on has been watching the project drag on for years.

“Every time I talk to the city I get a different reason, that they’re working on different design or the shoring,” he said.

From what Thorsteins­on can see there’s no work being done and equipment on the site is sitting idle.

“Whenever I go over (to talk to

Whenever I go over (to talk to the city) I just want them to fill it in and make a parking lot.

the city) I just want them to fill it in and make a parking lot,” he said.

According to Fortress, excavation work is complete on the fifth and final level of the undergroun­d parkade. Once shoring of the bottom is complete, concrete pouring will begin. The new timeline for the project to be finished is by spring 2019, rather than late 2018.

 ?? MICHAEL BELL / REGINA LEADER-POST. ?? Views of the Capital Pointe constructi­on site, which aren’t pleasing for a neighbour.
MICHAEL BELL / REGINA LEADER-POST. Views of the Capital Pointe constructi­on site, which aren’t pleasing for a neighbour.

Newspapers in English

Newspapers from Canada