South Shore Breaker

MODL awards site developmen­t tender to Dexter Constructi­on

Council unanimousl­y approves $305,550 contract to start project

- JOSH HEALEY editor@southshore­breaker.ca

The Municipali­ty of the District of Lunenburg (MODL) is one step closer to breaking ground on their new municipal building.

Council met on April 2 to award Dexter Constructi­on the tender for the site’s developmen­t, the first phase of its $ 7.2 million constructi­on project.

A call for bids was put out in March.

Andrew Amos, a senior partner from Catalyst Consulting Engineers working with the municipali­ty, said four contractor­s expressed interest in the work.

Ultimately, only three submitted bids and the numbers ranged from $291,000 to $535,000.

Dexter Constructi­on’s bid, the lowest of the group, came in at $291,000 plus HST; MODL had previously budgeted $400,000 for site developmen­t.

Atlantic Road Constructi­on & Paving and Brycon Constructi­on submitted the other two bids.

“This tender really consisted of two elements. One element is stripping the ground and the other is importing the shot rock,” Amos told council.

He said that the small number of variables actually increased the variance.

Given the winning bid, Amos said it was good value for money.

“Dexter has a proven track record for works such as this and

we anticipate no issues with them,” he said, adding that the company could begin work immediatel­y.

The motion was carried unanimousl­y by council and allowed for a change order of up to five per cent for constructi­on costs.

Including the change order, council approved a total cost of $305,550.

Council had previously made the decision to construct a new municipal building on Mar. 12, voting to replace MODL’S current facility on Aberdeen Road.

The new building will be built on municipali­ty owned land in Osprey Village.

In a previous interview with the South Shore Breaker, Mayor Carolyn Bolivar-getson said the municipali­ty would not go in debt to fund the project.

“This will not increase the tax rate and this definitely will not incur debt. We’re still onside to be debt free by 2021,” she said.

The new municipal building is expected to be completed by the spring of 2020.

 ?? Contribute­d ?? An artist’s rendition of MODL’S $ 7.2 million municipal building in Osprey Village.
Contribute­d An artist’s rendition of MODL’S $ 7.2 million municipal building in Osprey Village.
 ??  ??

Newspapers in English

Newspapers from Canada