The Chronicle Herald (Provincial)

Mill will close without extension, company says

- FRANCIS CAMPBELL fcampbell@herald.ca @frankscrib­bler

Northern Pulp's paper mill operations in Pictou County will shut down if the Boat Harbour deadline is not extended beyond Jan. 31, says a company executive.

“Northern Pulp Nova Scotia will be forced to notify its workforce and suppliers that if the government of Nova Scotia does not extend the Boat Harbour Act deadline for use of the Boat Harbour effluent treatment facility, the company will take the necessary steps to shut down the facility,” Brian Baarda, chief executive officer of Paper Excellence Canada, Northern Pulp Nova Scotia's parent company, said in a statement Thursday.

“Without such decision from the government of Nova Scotia,

our stakeholde­rs need to be ready for the worst-case scenario, including the terminatio­n of more than 300 employees, and the cancellati­on of contracts with suppliers, contractor­s, and woodlot operators throughout Nova Scotia, which will have an impact on more than 11,000 jobs in Nova Scotia alone,” Baarda said in his statement.

Premier Stephen McNeil will make his decision public Friday regarding a possible extension to the Boat Harbour Act.

“The regulator has given the company the opportunit­y to file an environmen­tal assessment report, which could take up to two years,” McNeil said in a statement released Wednesday morning.

“Our government now faces a very difficult decision — whether to give the company an extension to allow it to do the work necessary to prove it can operate in an environmen­tally sound manner, or let the Boat Harbour deadline stand, effectivel­y shutting down the mill.”

McNeil said he understand­s how difficult this is for many Nova Scotians for many different reasons.

The regulator, Environmen­t Minister Gordon Wilson, on Tuesday withheld approval of Northern Pulp's focus report in support of its proposed effluent treatment facility that would discharge treated effluent into the Northumber­land Strait.

Wilson said he concluded that more science-based evidence is needed to properly assess the potential risk to air, water, fish and human health.

The existing government­owned Boat Harbour effluent treatment plant has been in operation since the mill opened in 1967 but it is legislated to close on Jan. 31, 2020, predicated on an agreement reached between the provincial Liberal government and Pictou Landing First Nation more than five years ago.

“We urge the premier of Nova Scotia to extend the Boat Harbour Act deadline and ensure a continued future for a sustainabl­e and prosperous forestry sector in the province,” Baarda said in his statement.

“We continue to believe that Pictou County deserves to have both a clean environmen­t and a prosperous economy, and that Boat Harbour needs to be closed and remediated. An extension to the Boat Harbour Act deadline while a new world-class wastewater treatment facility at Northern Pulp is constructe­d is vital to achieving this. Once complete, the new treatment facility would allow operations in

Boat Harbour to cease, enabling federal and provincial remediatio­n of the former estuarine lagoon.”

The mill's focus report stated that effluent to be treated at the plant proposed for constructi­on on mill property will be piped to an outfall four kilometres from shore at Caribou, achieving better dilution than is the case with the effluent that is currently discharged from the Boat Harbour facility. The 245-page focus report claimed that the 85-million litres of treated effluent being discharged daily into the Northumber­land Strait would not harm marine species in the vicinity.

The company has said in the past that it would take at least 18 months to build the new effluent treatment facility and the 15-kilometre pipeline once it receives the government go-ahead.