The Niagara Falls Review

New transforme­r installed following fire at Meridian Community Centre

- VICTORIA NICOLAOU

Pelham will tap Meridian Community Centre (MCC) reserve funds to finance the cost of replacing a transforme­r damaged by fire last month that is not covered by insurance.

An investigat­ion into the cause of the fire is ongoing.

On April 4, the transforme­r at the community centre caught fire, causing power loss through the entire arena complex, resulting in the cancellati­on of a weekend of events, including the annual Fonthill Kinsmen Home and Garden Show.

A temporary portable generator was installed the following day, restoring power and enabling MCC to operate fully.

In the following days, the town said the transforme­r was damaged beyond repair, requiring the purchase of a replacemen­t.

During Wednesday’s town council meeting, public works director Jason Marr said a new, permanent transforme­r was installed on April 26.

Asked about the cause of the fire, Marr told councillor­s that “the insurers have a team of engineers and investigat­ors that are looking into it, but, at this point, we don’t have an answer.”

The old transforme­r has been shipped to the town's public works yard, where it will stay until the investigat­ion is complete.

Soon after the fire, an electrical contractor and Hydro One recommende­d to town staff that the MCC transforme­r unit be reduced to 1,000 kVA (volt-amps) from its original 2,000 kVA.

Usage reports showed that MCC’s largest draw was 680 kVA.

A report to council said the smaller equipment will allow the community centre to operate fully, and potentiall­y lower electrical costs.

The estimated cost to replace the transforme­r is anticipate­d to be about $385,000.

Town insurance is expected to cover the bulk of the bill, leaving about $100,000 uninsured. Council agreed to pay the remainder from its MCC reserve, for which its balance was $393,340 as of Dec. 31, 2023.

The report said the total loss of revenue due to the fire is unknown, but said estimated costs to run the facility with the portable generator was $30,000 a week.

It also said the rental revenue lost — from April 4 to 8 — was $7,674, plus an additional $1,548 from April 11, when a generator caused MCC power to fail.

The original transforme­r was owned and maintained by the Town of Pelham, but the new unit was purchased through Hydro One, with a maintenanc­e and operation agreement.

 ?? DAVE JOHNSON WELLAND TRIBUNE ?? The Meridian Community Centre transforme­r caught fire on April 4, causing a loss of power through the facility.
DAVE JOHNSON WELLAND TRIBUNE The Meridian Community Centre transforme­r caught fire on April 4, causing a loss of power through the facility.

Newspapers in English

Newspapers from Canada