Water supply tunnel into new phase

Design work begins this year on conduit under Stanley Park to replace one almost 90 years old

- JENNIFER SALTMAN jensaltman@postmedia.com twitter.com/jensaltman

Detailed design work will begin later this year on a critical water supply tunnel that will run under Vancouver’s Stanley Park.

“The project is really important to supplying water to the Metro Vancouver area, and it is through a crown jewel park,” said Goran Oljaca, director of engineerin­g and constructi­on with Metro Vancouver water services.

A water main — known as Capilano Main No. 4 — already runs through the park. It is almost 90 years old and carries water from the Seymour-Capilano Filtration Plant to Vancouver, the Musqueam First Nation, Richmond, Delta and the Tsawwassen First Nation — about half of the water used in the City of Vancouver and onethird of the region’s drinking water.

The steel main, which is 1.8 metres in diameter, has experience­d only minor leaks over the years, with the exception of a major breach near Lost Lagoon in August 2016. That took nearly a month to repair.

At that time, it was determined that the steel water pipe was reaching the end of its serviceabl­e lifespan. Oljaca said Metro pipelines typically are designed and built to last anywhere between 80 and 100 years, but newer ones can last longer.

The new 1.4-kilometre tunnel will run from Burrard Inlet west of Lumbermen’s Arch to near Chilco and Alberni streets, 40 to 60 metres underneath the park and Lost Lagoon. The new main, which will be 2.8 metres in diameter, is expected to have twice the capacity of the old one. The constructi­on budget is around $125 million.

Oljaca said the new tunnel will be constructe­d using three shafts. The main one, where most of the work will take place, could be located north of the city’s service yard. Two exit shafts would be located at the north and south ends of the park.

“I think the important thing is Metro Vancouver, or Greater Vancouver Water District, is working closely with the City of Vancouver, the park board, and First Nations to make sure we do this important project and at the same time minimize impact of the constructi­on,” Oljaca said.

Tiina Mack, the Vancouver park board’s manager of park developmen­t, said the collaborat­ion has worked well so far. She said the board and Metro Vancouver staff are in contact regularly.

“It’s our role to take care of this park and make sure the project is done in a sustainabl­e and safe manner for the park and its users,” Mack said.

Mack said it is important that the city, First Nations, Metro Vancouver and residents are working together to enhance the environmen­t in Stanley Park as part of the project.

The project is currently in the preliminar­y design stage.

Late last year, Metro Vancouver conducted preliminar­y ground investigat­ion work at six sites along the tunnel route. Oljaca said the geotechnic­al informatio­n shows that ground conditions are as expected.

That informatio­n will help Metro with the preliminar­y design, which is expected to be complete by October of this year. At that point, detailed project design will begin and last until late 2020. That is when Metro will issue a request for quotations and then a request for proposals. Constructi­on should start in 2021 and continue until 2025.

 ?? ARLEN REDEKOP/PNG ?? Tiina Mack, the Vancouver park board’s manager of park developmen­t, at Stanley Park’s Lost Lagoon, says the board is in regular contact with Metro Vancouver staff on the progress of a new water supply tunnel.
ARLEN REDEKOP/PNG Tiina Mack, the Vancouver park board’s manager of park developmen­t, at Stanley Park’s Lost Lagoon, says the board is in regular contact with Metro Vancouver staff on the progress of a new water supply tunnel.