The Standard (St. Catharines)

Water levels to surpass those of 2017

NOTL looking for temporary and long-term solutions

- MELINDA CHEEVERS

The Town of Niagara-on-theLake is putting precaution­s in place to address high water levels in Lake Ontario and the Niagara River.

When faced with a similar situation two years ago, staff thought at the time it was a ‘oneoff’ scenario. High water levels led to serious flooding along the dock area and shoreline erosion along the town’s entire shore — which stretches from its border with St. Catharines across the length of town, through to Queenston.

“We thought it was a fluke but here we are two years later and we’re facing the same thing,” said Brett Ruck, NOTL’s irrigation and draining superinten­dent manager of environmen­tal services.

In 2017, the water level in Lake Ontario was at 75.86 metres in May, according to Niagara Peninsula Conservati­on Authority — the highest level recorded since 1918. The price tag from floodingre­lated costs in 2017 surpassed $537,000 by the end of August.

Speaking during a presentati­on at a special council meeting at town hall Saturday morning, Ruck said the town has been given prediction­s that water levels could surpass those of 2017 and are expected to be at their highest in mid- to late June.

“There may be homes that may be directly impacted,” he said, especially if water levels go the predicted 10 inches higher than 2017. “The projection­s we’re seeing shows that.”

He said recovery of ‘normal’ elevation wouldn’t be until November, noting in 2017 water levels returned to normal in September.

Operations director Sheldon Randall said flooding protection and erosion measures have been put into place along the town’s waterfront. Right now there are plans to offset/prepare for flooding.

Sandbags have been made available to residents throughout the dock area, and pumps have been installed. Ruck said the town went with larger pumps than those used in 2017 with the hope they will be more effective. Putting the pumps in place early, rather than waiting for the water to rise further, meant there were more options available.

Large rocks were moved to the shoreline to offset water levels and work is being done to address erosion. Stone levels have been increased along various parts of the water front and a water bladder has been installed.

Randall said a report to addresses a long-term solution will be forthcomin­g.

Staff has been working towards strengthen­ing the shoreline, with a number of projects outlined. Some, including a culvert restoratio­n funded through the town’s capital budget and a Canada 150 grant, are completed. Other phases of the plan include installati­on of base rubble for wave action protection, boulder splash pads, reinforcin­g armour stone walls and the creation of a rain garden.

Randall said the town will be looking to various granting programs through each level of government and other funding agencies to find funds to complete the projects. These projects, as well as other long-term solutions, will be outlined in the report to come before council.

 ?? BOB TYMCZYSZYN TORSTAR FILE PHOTO ?? This May 2017 photo shows the effects of flooding caused to Ricardo Street.
BOB TYMCZYSZYN TORSTAR FILE PHOTO This May 2017 photo shows the effects of flooding caused to Ricardo Street.

Newspapers in English

Newspapers from Canada